Final | 8/22/2019 | 8/22/2019 | 8/22/2019 | A | PASS |
Eric Story
|
|
|
Final Inspection on Building E Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Occ card signed BLD E final ok
|
Electrical Rough-In | 7/25/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Eric Story
|
|
|
Building E rough in (partial final) in units 104, 105, 106, 107, 204, 205, 206, 207,304, 305, 306, 307 Phone #: ###-#### Inspection requested via web by Scott Wilson Partial final on west side units ok. Appliances not set at this time.
|
Electrical Rough-In | 7/25/2019 | 7/25/2019 | 7/25/2019 | P | CANC |
Eric Story
|
|
|
Building E, Units: 104, 105, 106, 107, 204, 205, 206, 207, 304, 305, 306, 307 Contact Scott Wilson Thank you, Phone #: ###-#### >> Inspection requested via web by Cathy Duchek Inspection cancelled from web by: Scott Wilson
|
Electrical Rough-In | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PART |
Eric Story
|
|
|
Rough In for 4 Units 100,101,102,103, 200,201,202,203,300,301,302,303 Contact electrician Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Units as requested are checked out and ok to move furniture in but not occupy
|
Electrical Rough-In | 6/21/2019 | 6/21/2019 | 6/21/2019 | P | PASS |
Rock A. Hudson
|
|
|
North entrance monument sign in center of round-a-bout wall conduits rough in ok cover.
|
Electrical Rough-In | 6/21/2019 | 6/21/2019 | 6/21/2019 | A | NH |
Rock A. Hudson
|
|
|
Monument Sign Rough In Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Unable to locate work, called in on permit for building completed with no work around it. No answer when called contact. Recall
|
Electrical Rough-In | 4/22/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Eric Story
|
|
|
Building E drop ceiling rough in for cover in Units 104, 105, 106, 107, 204, 205, 206, 207, 300, 304, 305, 306 and 307 Contact Scott Wilson Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Unots as requested drop ceilings ok to cover
|
Electrical Rough-In | 4/22/2019 | 4/23/2019 | 4/22/2019 | A | CANC |
Eric Story
|
|
|
Building E drop ceiling rough in for cover in Units 104, 105, 106, 107, 204, 205, 206, 207, 300, 304, 305, 306 and 307 Contact Scott Wilson Thank you Phone #: ###-#### >> Inspection requested via web by Cathy Duchek Inspection cancelled from web by: Cathy Duchek
|
Electrical Rough-In | 4/2/2019 | 4/3/2019 | 4/3/2019 | P | PASS |
Eric Story
|
|
|
Rough in for cover in Building E, Drop ceilings, Units 100, 101, 102, 103, 200, 201, 202, 203, 300, 301, 302, 303 Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Units as requested drop ceilings only ok to cover
|
Electrical Rough-In | 2/11/2019 | 2/11/2019 | 2/11/2019 | A | PASS |
Eric Story
|
|
|
Rough In inspection in Riser Room Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Riser room ok to cover
|
Electrical Rough-In | 2/11/2019 | 2/11/2019 | 2/11/2019 | P | PASS |
Eric Story
|
|
|
Rough In inspection in Riser Room Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Discussed documentation of non-GFCI protection for heaters and ground source for insurance
|
Electrical Rough-In | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | PASS |
Eric Story
|
|
|
Building E Rough in Units 104,105,106,107, and 204,205,206,207, and 304,305,306,307. Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Units as requested ok to cover
|
Electrical Rough-In | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | PASS |
Rock A. Hudson
|
|
|
Building E Rough in for Cover in the breezeways and Units 100, 101, 102, 103, 200, 201, 202, 203, 300, 301, 302, 303 Contact Scott Wilson Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Units as noted and both breezeways rough in ok cover
|
Permanent Service | 1/30/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Eric Story
|
|
|
Building E Service Inspection Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek p/s u/g n ok
|
Electrical Rough-In | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | PASS |
Eric Story
|
|
|
Ufer ground inspection for Building E Contact Scott Wilson Thank you Phone #: ###-#### Inspection requested via web by Tom Betty Ufer ok to cover
|