Final | 5/2/2019 | 5/3/2019 | 5/3/2019 | A | PASS |
James Ady
|
|
|
Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Corrections made final ok
|
Final | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | FAIL |
James Ady
|
|
|
Tobias is the contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker 110.26D lighting around panel board shall not be controlled by automatic means
|
Electrical Rough-In | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
James Ady
|
|
|
We need a grid inspection. Tobias is the site contact, thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Correction made ceiling ok to cover
|
Electrical Rough-In | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | FAIL |
James Ady
|
|
|
We need a grid inspection, Tobias is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Open J-box. (Water heater)
|
Electrical Rough-In | 4/1/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
James Ady
|
|
|
We need a ceiling rough. Tobias is the site contact, thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker New soffits in front and back of building ok to cover
|
Electrical Rough-In | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
James Ady
|
|
|
Tobias Phone #: ###-#### Walls only ok to cover
|
Electrical Rough-In | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | PASS |
James Ady
|
|
|
Tobias Phone #: ###-#### Exterior walls only ok to cover
|
Electrical Rough-In | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
James Ady
|
|
|
We need an underground inspection. Tobias is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker Underground to floor recep only ok to cover
|