Final | 7/19/2019 | 7/19/2019 | 7/19/2019 | A | PASS |
Eric Story
|
|
|
Will be on-site making equipment connections by 8 am. Should completed by 10 Phone #: ###-#### Inspection requested via web by Sean Patton New permit required for install of equipment. Occ card signed Final ok
|
Final | 7/17/2019 | 7/18/2019 | 7/18/2019 | A | NR |
Rock A. Hudson
|
|
|
I will be onsite by 8 am. Phone #: ###-#### Inspection requested via web by Sean Patton FRP repair, Covers off boxes. will recall.
|
Electrical Rough-In | 6/25/2019 | 6/26/2019 | 6/26/2019 | A | PASS |
Eric Story
|
|
|
Approval for cover in rooms with grid. I will be onsite at 9:30 Phone #: ###-#### Inspection requested via web by Sean Patton Areas with suspended ceiling are ok to cover
|
Rough-In Permanent Service | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PASS |
Rock A. Hudson
|
|
|
I will be on-site after 11 and throughout the day Phone #: ###-#### Inspection requested via web by Sean Patton Service only. Grounding electrode conductor to underground metal water pipe shall be sized to the total of parallel conductors as per 250.66. Will check in future due to supplemental electrodes installed. Availiable fault current will be verified in future due to Idaho Power has not provided transformer or service entrance conductors yet. Fused disconnecting means installed. p/s u/g n ok
|
Electrical Rough-In | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Eric Story
|
|
|
Wall inspection for cover. Late afternoon is best. I will not be back to site until 1pm. Phone #: ###-#### Inspection requested via web by Sean Patton Walls only ok to cover
|
Rough-In Permanent Service | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Mark Moncarr
|
|
|
Underground inspection for cover. Section of underground work is near the alley South end of building. I will not be onsite. GC has office in downstairs basement. His number is ###-#### Phone #: ###-#### Inspection requested via web by Sean Patton Ok cover 4-2" conduits. 4th conduit was added for LV.
|