Final | 7/3/2019 | 7/5/2019 | 7/5/2019 | A | PASS |
Tom Saunders
|
|
|
Patrick is the contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...ok to final
|
Permanent Service | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Eric Story
|
|
|
Patrick is the site contact, Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker p/s u/g n ok
|
Electrical Rough-In | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | PASS |
Eric Story
|
|
|
We need an underground inspection, Pat is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Secondary conduits to switch gear ok to cover
|
Electrical Rough-In | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | PASS |
Tom Saunders
|
|
|
We need an underground inspection, Bob is the site contact, ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker... ok to cover feeder pipes
|