Permit Information
Permit NumberELE19-01965
StatusFinaled
Name AURIC SOLAR
Site Address 165 S FIVE MILE RD
Project Name 
Customer Number 
ePlanReviewNo
Description
Addition: Roof Mounted Grid Tied Solar Panels
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final6/25/20196/25/20196/25/2019PPASS
DetailsTom Saunders
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior as we will need to meet you onsite to pull one panel and verify along with micro-inverter. Thank you for working with us on this. Rob Inspection requested via web by Rob Maes...
Labelling, disconnect, and OCPD ok
Electrical Rough-In6/24/20196/25/20196/25/2019APASS
DetailsTom Saunders
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior as we will need to meet you onsite to pull one panel and verify along with micro-inverter. Thank you for working with us on this. Rob Inspection requested via web by Rob Maes...
ul listed equipment verified
Final6/18/20196/19/20196/19/2019AFAIL
DetailsTom Saunders
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes...

Boise City requires a rough inspection before a final inspection can be requested
this is not contractors first job in Boise City and is fully aware of requirement
materials on roof will be removed and placed on ground for rough inspection...tiles, inverters, etc.
a reinspection fee will be applied to permit and needs paid before future inspections scheduled