Final | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | PASS |
James Ady
|
|
|
Install complete per approved plans; the stamped and approved plans are on site at the disconnect; For any questions about the work done for this project, call Jed at ###-####; For any questions about the plans or design, call Ryan at ###-####; thanks guys
The homeowner will be there to give access to the garage and you can give them a call on your way over at ###-#### Phone #: ###-#### Inspection requested via web by Ryan King Added panels to system. Final ok
|
Electrical Rough-In | 10/28/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Eric Story
|
|
|
listing inspection for solar equipment; the guys will be there around 12 pm but not sooner.
PLEASE NOTE - THIS PROJECT IS AN ADDITION; so there will already be old panels on the roof. We have not started the additional panels until we get the listing inspection. Our last rough in was failed because the guys had left the site and the inspector saw that panels were already up. Give me a call if you have any questions, thanks guys Phone #: ###-#### Inspection requested via web by Ryan King Listing of panels for addition of Solar Array panels to existing system ok
|
Electrical Rough-In | 10/21/2019 | 10/22/2019 | 10/22/2019 | P | FAIL |
James Ady
|
|
|
Listing inspection for solar equipment; The racking, cable management and penetrations are visible, with solar panels and inverters on the ground for viewing; The crew will be there from 10 to 4 Phone #: ###-#### Inspection requested via web by Ryan King No body onsite No equipment to see.
|
Electrical Rough-In | 10/14/2019 | 10/18/2019 | 10/14/2019 | A | CANC |
James Ady
|
|
|
Listing inspection for solar equipment; The racking, cable management and penetrations are visible, with solar panels and inverters on the ground for viewing; The crew will be there from 8 to 1 Phone #: ###-#### >> Inspection requested via web by Ryan King Inspection cancelled from web by: Ryan King
|