DOC - Permit Finaled | 5/13/2016 | 5/13/2016 | 5/13/2016 | P | PASS |
Andy J. Long
|
|
|
Townhome construction/earthwork complete. Exterior stabilized, landscaped, and sidewalks/alley cleaned. Temp BMP DI bags to remain installed and Blvd townhomes continue. Multiple SFHs in progress by Tahoe Homes.
|
Random Inspection | 5/13/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Bob Reichert
|
|
|
looked ok
|
Site Preparation | 11/4/2015 | 11/4/2015 | 11/4/2015 | P | PASS |
Andy J. Long
|
|
|
clint Phone #: ###-####
Approved for construction,scheduled to begin tomorrow or Friday. Permit signs posted, additional BMPs in process of being installed including:
-DI bags x2 on alley behind construction - lined concrete washout (first 3 homes used washout in DHE #12) - permiter wattle along the south edge/sidewalk - silt fence/construction fencing to control trackout and access to lots from alley. Allowed to be untrenched as it is intended as an administrative control rather than sediment control.
Approved. Tahoe Homes projects currently in compliance.
|