Site Final | 4/11/2017 | 4/14/2017 | 4/14/2017 | P | PASS |
Melissa Jannusch
|
|
|
DI bag has been removed. okay to final.
|
BMP Violation | 4/7/2017 | 4/11/2017 | 4/11/2017 | A | PEND |
Andy J. Long
|
|
|
Need to pull DI bags. Final request w/o fees to RP-GC to remove all temporary BMPs and sweep parking area.
Site final scheduled for Friday
|
Site Final | 3/31/2017 | 4/7/2017 | 4/7/2017 | P | FAIL |
Melissa Jannusch
|
|
|
No corrections that were requested have been done. No response from RP from previous message. Follow up with BMP violation inspection next week.
|
Site Final | 3/17/2017 | 3/31/2017 | 3/31/2017 | P | FAIL |
Melissa Jannusch
|
|
|
Vegetation is complete. Pavers need to be swept. DI bag need to be removed from Targee st. Left message for RP requesting corrections to obtain final. Follow up scheduled for next week.
|
Aging Inspection | 3/17/2017 | 3/17/2017 | 3/17/2017 | | PASS |
Andy J. Long
|
|
|
WIP on remaining landscaping of 3 units at Bryn Mawr Cottages. No trackout or discharges. Trash contained. Some homes occupied and ESC permits finaled
To get Site Final, complete landscaping, sweep up parking lot and permeable pavers, and remove DI bag from MS4 on Targee . Left VM with RP-GC Gene
|
Site Preparation | 7/22/2016 | 7/22/2016 | 7/22/2016 | A | PASS |
Andy J. Long
|
|
|
BMPs installed. Permit sign posted. Approved for excavation. 6 total cottages at Bryn Mawr Cove
|