DOC - Permit Finaled | 9/28/2017 | 9/28/2017 | 9/28/2017 | P | PASS |
Andy J. Long
|
|
|
Home complete, landscaped, and stabilized. Temp BMPs for Harris Crossing to remain until all units complete.
|
Site Preparation | 3/17/2017 | 3/21/2017 | 3/21/2017 | P | PASS |
Melissa Jannusch
|
|
|
Construction entrance okay.
|
General Inspection | 3/9/2017 | 3/16/2017 | 3/17/2017 | P | FAIL |
Melissa Jannusch
|
|
|
WIP on SFH. Corrections requested. Sweep and preform concrete washout maintenance. Left message with RP requesting corrections.
|
Site Preparation | 3/8/2017 | 3/9/2017 | 3/9/2017 | A | PASS |
Melissa Jannusch
|
|
|
Met onsite with Kyle RP. Discussed BMP installation, trackout prevention, use of concrete washout. Okay to start. Follow up next week to ensure additional BMPs are installed. Signs are posted. Okay to start.
|