General Inspection | 12/18/2017 | 12/18/2017 | 12/18/2017 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 12/18/2017 | 12/18/2017 | 12/18/2017 | P | PASS |
Michael Zawacki
|
|
|
|
Site Final | 10/18/2017 | 10/18/2017 | 10/18/2017 | P | DONE |
Michael Zawacki
|
|
|
Final stabalization complete. All work complete.
|
General Inspection | 10/18/2017 | 10/18/2017 | 10/18/2017 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 6/29/2017 | 6/29/2017 | 6/29/2017 | A | PASS |
Andy J. Long
|
|
|
WIP on interior. Parking lot and permeable pavers are now installed. Area being used for staging. NO loose dirt, spills or discharges. Permit sign posted
|
General Inspection | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Melissa Jannusch
|
|
|
WIP. Soil is not stable yet. No ESC issues
|
General Inspection | 4/28/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Andy J. Long
|
|
|
WIP. Rock construction access and staging area provided. Permit sign posted. No discharges or trackout.
|