Site Final | 11/2/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 5/16/2017 | 5/16/2017 | 5/16/2017 | A | PASS |
Andy J. Long
|
|
|
Rotary Plaza in progress. Path leading south to river is now complete. Work and staging area are clean, surrounding vegetation is preserved. Concrete washout and inlet protection BMPs are in good condition.
|
General Inspection | 3/22/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Melissa Jannusch
|
|
|
SWPPP available. disturbance surrounded by vegetation. Concrete washout on site. No corrections
|
Site Preparation | 3/17/2017 | 3/22/2017 | 3/22/2017 | P | PASS |
Andy J. Long
|
|
|
Onsite meeting with RP Leland and project manager Adrian.
Permit sign now posted on SWPPP sign at staging area. Staging area is fenced in and will house equipment, concrete washout, and trash facility. Trees have already been removed. Using Julia Davis Park central path as long stabilized entrance. Will plan on having sweeping unit available for any trackout or dust issues occuring.
Park vegetataion surrounding construction area to be preserved. Two storm drain inlets in front zoo have filter bag protection installed.
Approved for construction.
|
Site Preparation | 3/17/2017 | 3/17/2017 | 3/17/2017 | A | PEND |
Andy J. Long
|
|
|
No work or staging started. Informational signs about the Rotary Grand Plaza are posted. Will check next week.
|