Permit NumberESC17-00891
StatusFinaled
Name JAMIE MARTZ
Site Address 2200 W FAIRVIEW AVE
Project NameNew Path Community Housing
Customer Number 
ePlanReviewNo
Description
New Path Community Housing: To demolish existing 6,061 sf restaurant building and to construct a new 34,249 sf, 4-story, 41-unit multi-family apartment building and site improvements. RP TBD. Straw wattle perimeter controls, interior inlet protection in parking lot.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection12/4/201812/4/201812/4/2018 CANC
DetailsMichael Zawacki
DOC - Permit Finaled12/4/201812/4/201812/4/2018PPASS
DetailsMichael Zawacki
General Inspection10/19/201810/19/201810/19/2018 PASS
DetailsMichael Zawacki
Prepping for parking lot. Pile of pit run is on road, currently being brought onto site. Very little dust, no dirt being tracked from work area.
General Inspection9/3/20189/3/20189/4/2018 PASS
DetailsMichael Zawacki
Site is contained. Workers prepping planter boxes along main st. No dirt or dust leaving site.
General Inspection7/17/20187/17/20187/17/2018PPASS
DetailsMichael Zawacki
Site is contained, most of work area is below grade. Dumpster on site, no loose trash. Material storage all within disturbed area.
General Inspection6/12/20186/12/20186/12/2018PPASS
DetailsMichael Zawacki
WIP on vertical construction. Site is below grade of sidewalk and has blown bark wattles. No trackout or trash leaving site. No dust.
General Inspection5/24/20185/24/20185/24/2018 PASS
DetailsMichael Zawacki
WIP on vertical. Site still surrounded by wood chip wattles, DIs are all protected. Storage and parking are all on paved lot. Site is clean.
Random Inspection1/4/20181/4/20181/4/2018APASS
DetailsAndy J. Long
Surrounding MS4 inlets have sediment bag protection. No trackout or discharges observed. Vertical construction in progress.
Random Inspection12/18/201712/18/201712/18/2017PPASS
DetailsMichael Zawacki
perimeter control in tact. Cutting cinder blocks, saw has water system to prevent dust. No trackout or dust leaving site.
General Inspection11/29/201711/29/201711/29/2017PPASS
DetailsAndy J. Long
WIP on connecting underground utilities to site. No trackout or discharges.
Site Final11/29/201711/29/201711/29/2017PCANC
DetailsAndy J. Long