Site Final | 11/29/2018 | 11/30/2018 | 11/30/2018 | A | PASS |
Andy J. Long
|
|
|
Home complete and landscaped. No ESC corrections.
|
General Inspection | 8/23/2018 | 8/23/2018 | 8/23/2018 | P | PART |
Michael Zawacki
|
|
|
Foundation is completed, materials stored on lot. No BMPs installed along sidewalk, some dirt on sidewalk.
|
General Inspection | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Andy J. Long
|
|
|
Permit sign posted, no discharges or spills at site. Crew removing foundation form boards and cleaning up.
Correction request to RP Bobby to sweep street, sidewalk, and gutter once the form trailers habe been hauled off and area is open. He stated he will sweep this afternoon or tomorrow.
After backfill (before mid August), perimeter wattles will be installed.
|
Site Preparation | 7/6/2018 | 7/9/2018 | 7/9/2018 | A | PART |
Andy J. Long
|
|
|
WIP on excavation. Permit sign posted
Corrections needed: - install perimeter wattles on bottom corner of lot below excavation - protect stockpile of backfill on upper lot - sweep sidewalk & gutter - provide concrete washout for foundation
|
Site Preparation | 7/6/2018 | 7/6/2018 | 7/6/2018 | P | PEND |
Andy J. Long
|
|
|
|
Site Preparation | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | NR |
Michael Zawacki
|
|
|
Bobby Phone #: ###-#### No BMPs installed, not ready for site prep inspection. Permit is displayed.
|