Site Final | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Michael Zawacki
|
|
|
check that all DI bags are removed around the albertson's site (Rossi & Grant)
|
General Inspection | 1/31/2019 | 1/31/2019 | 1/31/2019 | P | PASS |
Michael Zawacki
|
|
|
Building about 2/3 down. No dirt leaving site, water truck on site. No dust plumes, no neighbor complaints.
|
BMP Violation | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Andy J. Long
|
|
|
Water truck now onsite and in use for fugitive dust control as requested. Will continue to monitor.
|
Site Preparation | 1/29/2019 | 1/29/2019 | 1/30/2019 | P | FAIL |
Andy J. Long
|
|
|
No water truck onsite as requested previously in complaint inspection. Water truck needs to be onsite before 1 PM or will shut down site.
Some fugitve dust occuring.
Storm drains have sediment protection installed.
|
Complaint Inspection | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with foreman. No dust at time of inspection, they are bringing in water truck and will use as needed.
|