General Inspection | 8/13/2020 | 8/13/2020 | 8/13/2020 | | PASS |
Michael Zawacki
|
|
|
Area has been excavated for footing, nothing poured, no frames installed. Looks like some anchors for foundation have been installed. Stockpiled dirt covered with an ecb. No workers at site.
|
General Inspection | 7/29/2020 | 7/29/2020 | 7/29/2020 | | PASS |
Michael Zawacki
|
|
|
Washout has been cleaned, backfill replaced. Crew on site has started plumbing, waiting for inspection. Some backfill being loaded to be hauled. No major excavation yet.
|
General Inspection | 7/14/2020 | 7/14/2020 | 7/14/2020 | | FAIL |
Michael Zawacki
|
|
|
Washout dumped on each end of wall. Contacted RP, any future washout will result in fine.
|
Site Preparation | 6/26/2020 | 6/29/2020 | 6/29/2020 | A | PASS |
Michael Zawacki
|
|
|
Talked to Troy, ok to start. Hillside has wattles, vegetation, and coconut blanket. Will clean as they go, foundation will take up majority of area. First construction will be retaining wall.
|
General Inspection | 6/16/2020 | 6/16/2020 | 6/16/2020 | | PASS |
Michael Zawacki
|
|
|
No workers on site. Road work in front of lot on Cicle Way, not sure if county or site related. Trailer and mini excavator stored on lot.
|
General Inspection | 6/1/2020 | 6/1/2020 | 6/2/2020 | | PASS |
Michael Zawacki
|
|
|
No work has begun. To access home you need to go in off Horizon Drive, stairway leads down to circle.
|