INSP-Final Inspection | 9/12/2008 | 9/12/2008 | 9/12/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | PART |
Forrest France
|
|
|
Items on correction notice have been verified for completion, permit final pending tamper and alarm device testing.
|
INSP-Final Inspection | 9/9/2008 | 9/9/2008 | 9/10/2008 | P | FAIL |
Forrest France
|
|
|
Noted several spacing issues at the SW branch line adjacent to the overhead doors, missing PRV at the riser, trapeeze hanger at the last piece of 6" main is overspaced, FDC piping is missing hanger support and bracing at the vertical run, noted added head at the electrical room, provide riser tags, signage, DCVA certification, and complete forward flow testing in conjunction with riser supervision. Site inspection completed 9/9.
|
INSP-Final Inspection | 9/8/2008 | 9/8/2008 | 9/9/2008 | P | NR |
Forrest France
|
|
|
Need approved plans on site.
|
INSP-Sprinkler Rough-in/Hydro | 9/4/2008 | 9/4/2008 | 9/4/2008 | A | PART |
Forrest France
|
|
|
Repairs completed, UG fire supply line hydrostatic testing passed. Noted missing sprinkler piping and head coverage at the electrical room adjacent to the riser, also noted FDC is over max. 4' above grade due to finish slope-see fire code review notes item #51 for FDC requirements. Overhead install not inspected to date.
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2008 | 8/14/2008 | 8/14/2008 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2008 | 7/30/2008 | 7/30/2008 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed acceptable.
|
INSP-Sprinkler Rough-in | 6/3/2008 | 6/3/2008 | 6/3/2008 | P | PART |
Forrest France
|
|
|
UG fire suply line installation appears satisfactory however the city stamped drawings and documents were not on site at the time of inspection per condition of the permit, will need to verify plans match install prior to final approval.
|