INSP-Final Inspection | 10/3/2008 | 10/6/2008 | 10/6/2008 | A | PASS |
Forrest France
|
|
|
Three C/N items repaired, forward flow testing completed acceptable, fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/30/2008 | 9/30/2008 | 10/1/2008 | P | DEFR |
Forrest France
|
|
|
See inspection notes dated 10/1
|
INSP-Final Inspection | 9/30/2008 | 10/1/2008 | 10/1/2008 | A | FAIL |
Forrest France
|
|
|
Need to provide a PRV at the riser due to the grid system design, noted one leaking sprinkler drop above the restroom ceiling, forward flow testing of the DC backflow preventer failed.
|
INSP-Final Inspection | 9/24/2008 | 9/25/2008 | 9/25/2008 | P | CANC |
Forrest France
|
|
|
final Inspection - contact: Todd Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley NOTE: Inspection rescheduled per conversation with contractor pending fire alarm interconnections
|
INSP-Final Inspection | 9/23/2008 | 9/24/2008 | 9/24/2008 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled with the fire alarm testing.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2008 | 9/8/2008 | 9/8/2008 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic retest passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 9/4/2008 | 9/4/2008 | 9/4/2008 | A | NR |
Forrest France
|
|
|
Site visit confirmed repairs for leakage at overhead piping are not yet complete for re-test.
|
INSP-Sprinkler Rough-in/Hydro | 9/3/2008 | 9/3/2008 | 9/3/2008 | P | FAIL |
Forrest France
|
|
|
Overhead hydrostatic testing failed due to visible system leakage at four locations.
|
INSP-Sprinkler Rough-in/Hydro | 8/27/2008 | 8/27/2008 | 8/27/2008 | A | PART |
Forrest France
|
|
|
See stamped plan set for locations inspected and okayed for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/25/2008 | 8/26/2008 | 8/26/2008 | P | PART |
Forrest France
|
|
|
Overhead work at the drop ceiling and hard lid areas are approved for cover-see circled and initialed location on plans, noted one head to be adjusted due to minor overspacing at the hallway intersection, painted heads at the restrooms need to be replaced. Remainder of installation not yet inspected.
|
INSP-Conference | 8/8/2008 | 8/19/2008 | 8/19/2008 | A | DONE |
Forrest France
|
|
|
9:00 a.m. on site conference inspection with all trades - for any questions contact Jim Storey
|
INSP-Sprinkler Rough-in | 7/22/2008 | 7/22/2008 | 7/22/2008 | P | PART |
Forrest France
|
|
|
Site visit to verify seismic restraint at beam clamps for system piping hangers prior to structural fireproofing throughout.
|