Permit Information
Permit NumberFIR09-00384
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 2822 S VISTA AVE
Project NamePacific Cataract & Laser Insti
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of one new wet pipe system. There are sprinklers in the attic, in over build areas, below the mechanical room floor, in the mechanical room, and below the ceiling. Regular sprinklers and special application sprinklers are being utilized. There is a new 6" underground that was approved under FIR09-00347. There are three canopies that are to be completely filled with non combustible insulation. The lower level protection consists of a 4"x3"x 1½" grid. The upper level of protection consists of a two 3" loops with 1¼" lines.

_________

Building Scope:

Pacific Cataract & Laser Institute - To construct a new 9,365 square foot, one story with 1,285 square foot mechanical mezzanine, wood framed medical office building (outpatient eye clinic) and related site improvements. This building is fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/10/20102/10/20102/10/2010APASS
DetailsForrest France
Fire sprinkler work passed final walkthrough, permit finaled.
INSP-Final Inspection2/1/20102/1/20102/1/2010APART
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro11/27/200911/27/200911/27/2009APART
DetailsForrest France
Final pending project related FIR09-00347.
INSP-Sprinkler Rough-in11/16/200911/16/200911/16/2009PPART
DetailsForrest France
Overhead work approved for cover at the sheetrock ceilings throughout.
INSP-Sprinkler Rough-in11/9/200911/10/200911/10/2009APART
DetailsForrest France
Inspection to verify insulation fill at four concealed spaces, added upright protection at the south side for exposed wood above the drop ceiling, and previous C/N items completed okay. Discussed hydrostatic testing and job finish schedule.
INSP-Sprinkler Rough-in11/5/200911/5/200911/5/2009PPART
DetailsForrest France
Partial overhead cover approved as discussed.
INSP-Sprinkler Rough-in11/4/200911/4/200911/4/2009PPART
DetailsForrest France
Okay to cover except the SW area where combustible construction above the drop ceilings is exposed, noted one upright head to be relocated due to obstruction by a truss web at the attic area north side, insulation at two branchline feeds to dry sidewall heads adjusted while on site, remainder of previously noted correction items are finished, minor field modifications at some locations okayed, still need to verify insulation install at exterior canopies as discussed.
INSP-Sprinkler Rough-in11/2/200911/2/200911/2/2009PPART
DetailsForrest France
Inspection for cover at the hard lid ceilings for the first floor passed with the exception of annotated areas including a missing hanger, insulation to be moved, one incompleted branchline serving two rooms, added and deleted heads to be shown on record drawings, exposed wood above partition walls to be sheetrocked or protected with sprinklers, need to schedule inspeciton for insulation fill at concealed pockets.
INSP-Sprinkler Rough-in10/29/200910/30/200910/30/2009APART
DetailsForrest France
See stamped plan set for areas of the attic system piping inspected and okayed -marked with today's date.
INSP-Sprinkler Rough-in10/28/200910/29/200910/29/2009PCANC
DetailsTroy Cobbley
Overbooked. Rescheduled with Jake for tomorrow.
INSP-Sprinkler Rough-in/Hydro10/20/200910/20/200910/20/2009APART
DetailsForrest France
Jake Phone#: ###-####
INSP-Sprinkler Rough-in/Hydro10/19/200910/19/200910/19/2009PPART
DetailsForrest France
See annotations on plan set marked with today's date for inspection notes including two blocked upright heads by adjacent truss web members, insulation at the deck needs lifted away from deflectors at two heads, install baffle or relocate two heads which exceed min. spacing. Discussed seismic bracing and coverage at the front entry vestibule. Noted correction items from the previous inspection are finished.
INSP-Sprinkler Rough-in10/14/200910/15/200910/15/2009AFAIL
DetailsTroy Cobbley
Inspection performed by tim. Per tim there was missing piping, sprinkler heads, branchline restraints........ect. Only the south 1/3 of the building was inspected as requested by fire sprinkler contractor and as directed by the job superintendant. No piping can be covered until re-inspection.
INSP-Sprinkler Rough-in10/14/200910/14/200910/14/2009PCANC
DetailsTroy Cobbley
Overbooked. I spoke to Jake and will reschedule for tomorrow.
INSP-Sprinkler Rough-in/Hydro10/13/200910/14/200910/14/2009AFAIL
DetailsTroy Cobbley
No one answered the contact phone number and when I got to the project I could not find any sprinkler fitters. No inspection was performed.
INSP-Sprinkler Rough-in/Hydro10/5/200910/5/200910/5/2009ANR
DetailsForrest France
Work in progress, construction underway.
FIR-Aging Inspection9/25/20099/25/20099/25/2009 DONE
DetailsForrest France
In progress