INSP-Final Inspection | 7/27/2010 | 7/28/2010 | 7/28/2010 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/13/2010 | 7/14/2010 | 7/14/2010 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the revised risers. The new inspectors tests and flow switches functioned correctly. Also inspected were the phase 13 sprinkler piping which can be covered. Sprinkler coverage is lacking in an entry foyer in this same area.
|
INSP-Sprinkler Rough-in | 7/1/2010 | 7/2/2010 | 7/2/2010 | A | PART |
Troy Cobbley
|
|
|
Phase II sprinkler work is complete. We could not test the devices at the modified riser because of no access to the inspectors test in PoJo's and the correct orfice in the Dept. of Health/welfare was missing.
|
INSP-Sprinkler Rough-in | 6/11/2010 | 6/11/2010 | 6/11/2010 | P | PASS |
Troy Cobbley
|
|
|
Phase 10 sprinkler piping is complete.
|
INSP-Sprinkler Rough-in | 5/13/2010 | 5/14/2010 | 5/14/2010 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinkler risers #2 and #3 inspected today. Flow switches and tamper switches functioned correctly. Noted that the backflow preventors need their certifications.
|
INSP-Sprinkler Rough-in | 3/23/2010 | 3/24/2010 | 3/24/2010 | A | PASS |
Troy Cobbley
|
|
|
The phase 8 sprinkler piping is passed.
|
INSP-Sprinkler Rough-in | 1/14/2010 | 1/15/2010 | 1/15/2010 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was a partial for Area #6. See the city approved plans for this location clouded in red. Piping can be covered except for the two pendant heads that need to be added due to overspacing. These have been clouded as well.
|
INSP-Sprinkler Rough-in | 11/16/2009 | 11/16/2009 | 11/16/2009 | P | PASS |
Troy Cobbley
|
|
|
Phase 4 sprinkler piping is ok to cover. Two heads off of 1" piping is ok at this end of the building per Tim Frost. Note #10 of the review comments is a typ error.
|
INSP-Sprinkler Rough-in | 11/3/2009 | 11/3/2009 | 11/3/2009 | P | PASS |
Troy Cobbley
|
|
|
Phase 2 sprinkler piping can be covered. Insulation at the deck needs re-attached and will be verified at the building final.
|
INSP-Sprinkler Rough-in | 10/29/2009 | 10/30/2009 | 10/30/2009 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping for Phase 3 can be covered.
|