INSP-Final Inspection | 9/16/2011 | 9/16/2011 | 9/16/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 9/6/2011 | 9/6/2011 | 9/6/2011 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 9/1/2011 | 9/1/2011 | 9/1/2011 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2011 | 8/8/2011 | 8/8/2011 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping hydro test passed.
|
INSP-Sprinkler Rough-in | 7/29/2011 | 7/29/2011 | 8/1/2011 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
INSP-Sprinkler Rough-in | 7/28/2011 | 7/28/2011 | 7/28/2011 | P | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 7/27/2011 | 7/27/2011 | 7/27/2011 | P | PART |
Forrest France
|
|
|
See stamped plan set for dated red lines indicating location of work completed and approved for bury.
|
INSP-Sprinkler Rough-in | 7/25/2011 | 7/26/2011 | 7/26/2011 | P | PASS |
Troy Cobbley
|
|
|
Underground piping is ok to cover 60' from the first 22 degree fitting towards the building.
|
INSP-Sprinkler Rough-in | 7/25/2011 | 7/26/2011 | 7/26/2011 | A | PASS |
Troy Cobbley
|
|
|
Underground is ok to cover up to the 22 degree fitting
|
INSP-Sprinkler Rough-in | 7/25/2011 | 7/25/2011 | 7/25/2011 | P | FAIL |
Troy Cobbley
|
|
|
Arrived at job site but found that the piping installation of the underground is being delayed due to problems with other services. Troy said he would reschedule for tomorrow.
|
INSP-Sprinkler Rough-in | 6/14/2011 | 6/15/2011 | 6/15/2011 | A | PASS |
Troy Cobbley
|
|
|
The stub out only is ok to cover. This piping was lowered to meet the city and state requirement of atleast 4'6" to top of piping for a minimum bury.
|