Permit Information
Permit NumberFIR11-00671
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1195 N MILWAUKEE
Project NameNATURAL GROCERS
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of adding, deleting and relocating sprinklers to accommodate new wall and ceiling configuration. The existing system has a 6” udg supply, 3” wall piv and 3” backflow preventer. The system is a grid type layout with a 3” primary main, 2½” secondary main and 1½” branch lines. A portion of the existing 2½” secondary main is being rerouted and changed to 4”

Note: The owner’s certificate indicates there is to be NO storage exceeding 12’ in height.


Building Department Scope:

(NATURAL GROCERS) (CZC11-00225) This building has a fire sprinkler system for building area increase and for fire area. To remodel an existing 20,120 square foot building for a new retail sales tenant (grocery store). A demonstration kitchen classroom will be provided. It will be an A-3 Occupancy. A grease hood will be installed above the range. A grease trap will be installed on the sink. Work is to include 2 restrooms accessible to the disabled, a toilet/shower room accessible to the disabled, interior nonbearing walls, gypsum board bulkheads suspended from the roof deck, gypsum board ceilings, suspended acoustical ceilings, suspended wood ceilings, walk-in freezer and refrigerators, display shelving, millwork, and interior finishes. An air curtain will be installed at the entry vestibule. A 750 square office mezzanine will also be constructed. Structural work includes concrete footings, steel columns, steel floor joists, steel bracing rods, “forto-crete” floor sheathing, and a steel stairway. In addition, the existing steel roof trusses will be altered to increase their capacity to support added equipment loads on the roof. An interior nonstructural demolition and partial permit was issued on December 7, 2011. See BLD11-02862 for the extent of work allowed under that permit. The work is required to comply with the approved drawings, with the plan review report, with the structural calculations, and with all adopted codes and ordinances. Special Inspection is required for welding and epoxy anchors. Modifications to the existing steel roof joists and girders are required to be in accordance with the manufacturer’s specifications. A separate permit is required for storage racks where storage will be more than 8 feet above the floor. The structural design for the steel stairway is a deferred submittal item. The fire alarm is required to comply with NFPA 72 and the fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/10/20122/10/20122/10/2012PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection2/8/20122/9/20122/9/2012AFAIL
DetailsTroy Cobbley
Need verification of resubmittals and final paper work. Alarm testing is complete.
INSP-Sprinkler Rough-in/Hydro2/7/20122/8/20122/8/2012PPASS
DetailsTroy Cobbley
Hydro test passed.
INSP-Sprinkler Rough-in/Hydro2/6/20122/7/20122/7/2012PDEFR
DetailsForrest France
Richard is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in2/3/20122/6/20122/6/2012APART
DetailsTroy Cobbley
Part of the rough-in passed but others failed. There are two area of concern where additional fittings have been added and as requested by the approval notes plans will need to be resubmitted. Upright sprinkler protection is overspaced above the slatted ceiling at the north end of the store. A hydro test is also required.
INSP-Sprinkler Rough-in1/26/20121/27/20121/27/2012AFAIL
DetailsTroy Cobbley
Could not perform the inspection due to the city approved plans being locked in the job shack. Also the area that was being requrested had been changed per the fitter. I deferred the changes to Tim Frost.
INSP-Sprinkler Rough-in1/24/20121/25/20121/25/2012ACANC
DetailsTroy Cobbley
To be canceled per Nate
INSP-Sprinkler Rough-in1/20/20121/23/20121/23/2012APASS
DetailsTroy Cobbley
The piping above the hardlid areas is ok to cover.
INSP-Sprinkler Rough-in1/19/20121/20/20121/20/2012PCANC
DetailsTroy Cobbley
As late in the day as possible. Nate is the contact. Thanks Phone #: ###-#### Overbooked due to other inspections and Micron facilities plan review.