Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberFIR12-00116
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 12601 W BRIDGER ST
Project NameIDAHO POWER PHASE 1
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of a new 4” double interlock preaction system. The preaction valve feed a 3” main on a tree system with telescoping branch piping. A new 6” backflow preventer is to be added. The existing alarm valve is being relocated.



Building Department Scope:

IDAHO POWER PHASE 1 FPP permit previously MCI building built and finaled in 1994. Renovation of approximately 6000 sq ft to create a data floor complete with mechanical and electrical system upgrades and support space for IT distribution. Structure is fully engineered and designed for one hour construction that is not code driven but shall be constructed per plan. Fire alarm and sprinkler submittals are required to be submitted to the Boise City fire plan review for approvals. Inspections are to be direct contact with the inspectors. Building Jim Storey 794-9490/ Mechanical Troy James 794-9461/ Plumbing Jim Johnson 794-9476/ Electrical Daryl Degrange 794-1379/ Fire Forest France 794-1981
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/31/20127/31/20127/31/2012PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro6/19/20126/20/20126/20/2012PPASS
DetailsTroy Cobbley
24 hour air test passed for the pre-action system
INSP-Sprinkler Rough-in/Hydro6/19/20126/19/20126/19/2012PPART
DetailsTroy Cobbley
24 hour air test started at 1:30 with 44 psi on the guage.
INSP-Sprinkler Rough-in6/12/20126/13/20126/13/2012PPASS
DetailsTroy Cobbley
Overhead hydro tests on the dry and wet systems passed. Still need 24 hour air test on the dry. Rough-in for the sprinkler piping in the data room passed and the piping can be covered. The wet system piping rough-in passeed. Plan review needs to be contacted about modified hydraulic calculations due to the additional 2" elbows that have been added between the remote area and the supply.