INSP-Final Inspection | 7/31/2012 | 7/31/2012 | 7/31/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2012 | 6/20/2012 | 6/20/2012 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test passed for the pre-action system
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2012 | 6/19/2012 | 6/19/2012 | P | PART |
Troy Cobbley
|
|
|
24 hour air test started at 1:30 with 44 psi on the guage.
|
INSP-Sprinkler Rough-in | 6/12/2012 | 6/13/2012 | 6/13/2012 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro tests on the dry and wet systems passed. Still need 24 hour air test on the dry. Rough-in for the sprinkler piping in the data room passed and the piping can be covered. The wet system piping rough-in passeed. Plan review needs to be contacted about modified hydraulic calculations due to the additional 2" elbows that have been added between the remote area and the supply.
|