INSP-Final Inspection | 10/26/2012 | 10/29/2012 | 10/29/2012 | A | PASS |
Forrest France
|
|
|
Coverage adjustments verified. Fire sprinkler permit work complete, permit finaled.
|
INSP-Final Inspection | 10/23/2012 | 10/23/2012 | 10/23/2012 | P | FAIL |
Forrest France
|
|
|
Overspaced pendent coverage at three classrooms. Previous C/N items dated 10/5 verified for completion.
|
INSP-Sprinkler Rough-in | 10/4/2012 | 10/5/2012 | 10/5/2012 | A | FAIL |
Troy Cobbley
|
|
|
Provide "job site copy" city approved plans for inspection, three upright heads on two lines (six total heads) are blocked by truss webbing, branchline restraint is missing, earthquake bracing is missing, wrong extended coverage pendants have been installed which will require a plan modification, as-builts will atleast be needed to show the pipe routing changes, one upright head at the mezzanine walkway appears to be overspaced. Ceiling tile can be installed since items needing correction can be viewed from the mechanical walkway.
|