INSP-Final Inspection | 1/29/2013 | 1/30/2013 | 1/30/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 10/12/2012 | 10/12/2012 | 10/12/2012 | P | PASS |
Troy Cobbley
|
|
|
The heat tape assembly is ok to be covered.
|
INSP-Sprinkler Rough-in/Hydro | 10/9/2012 | 10/9/2012 | 10/9/2012 | P | PASS |
Troy Cobbley
|
|
|
OH hydro test passed for building 11
|
INSP-Sprinkler Rough-in | 10/8/2012 | 10/8/2012 | 10/8/2012 | P | PASS |
Troy Cobbley
|
|
|
Third floor sprinkler piping can be covered. Tenting has been repaired.
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2012 | 10/8/2012 | 10/8/2012 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test for all three systems failed.Performed the test twice.
|
INSP-Sprinkler Rough-in | 9/28/2012 | 10/1/2012 | 10/1/2012 | A | FAIL |
Troy Cobbley
|
|
|
Third floor tenting has not been repaired or completed. Piping can not be covered.
|
INSP-Sprinkler Rough-in | 9/28/2012 | 9/28/2012 | 9/28/2012 | P | PASS |
Troy Cobbley
|
|
|
Building 11, first and second floor rough-in passed and piping can be covered. Third floor can not be covered until the tenting has been modified. Areas that can not be covered are where the heat tape and associated wiring/control is located when it is installed.
|