Permit Information
Permit NumberFIR12-00574
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 12352 W FAIRVIEW AVE
Project NamePeterson Chevy of Boise
Customer Number 
ePlanReviewNo
Description
The fire sprinkler scope of work consists of providing two wet systems and one dry to system to protect a new car dealership. The system is a mixture of a grid and tree. There are flammable liquids in the parts storage and shop area.

The fire protection underground was installed under permit FIR12-00330.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/11/20134/12/20134/12/2013APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection4/11/20134/11/20134/11/2013PFAIL
DetailsTroy Cobbley
Forward flush passed inspection but can not final until the latest plans have been provided.
INSP-Final Inspection4/8/20134/9/20134/9/2013AFAIL
DetailsTroy Cobbley
The forward flush test failed and the plan modifications are not on site.
INSP-Sprinkler Rough-in4/2/20134/3/20134/3/2013APASS
DetailsTroy Cobbley
The 24hr air test on the dry system passed.
INSP-Sprinkler Rough-in/Hydro4/1/20134/2/20134/2/2013PPASS
DetailsTroy Cobbley
The oh hydro of the 4" riser/steim passed. The 24 hour air test of the dry system was startedat 12:00 with 44psi on the guage. Previous correction items in the shop areas have been corrected.
INSP-Sprinkler Rough-in/Hydro3/29/20133/29/20133/29/2013PPART
DetailsForrest France
Overhead hydrostatic testing of the new dry system, 6" riser, and FDC completed satisfactory.
INSP-Sprinkler Rough-in3/18/20133/19/20133/19/2013PPASS
DetailsTroy Cobbley
See the city approved plans for locations marked "ok" where piping can be covered.
INSP-Sprinkler Rough-in/Hydro3/14/20133/15/20133/15/2013APASS
DetailsTroy Cobbley
Under ground hydro test passed.
INSP-Sprinkler Rough-in3/6/20133/7/20133/7/2013APASS
DetailsTroy Cobbley
See the city approved plans for locations marked "ok" where sprinkler piping is ok to cover.
INSP-Sprinkler Rough-in/Hydro2/20/20132/21/20132/21/2013APART
DetailsForrest France
Mark J is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in2/20/20132/20/20132/20/2013PPART
DetailsTroy Cobbley
The original "job site copy" of plans with review notes and data sheets needs to be on site at the next inspection. I gave the ok to cover on the west side exterior canopy. The south and east canopy have been covered without any piping inspection. The contractor is now removing plywood for an inspection to be scheduled for tomorrow. I spoke to Odie, with Steed Const. about covering prior to rough-in inspections. I did look at one interor area, marked in red on the plans, and noted three items. One is a retaining strap needs installed correctly, the other is flexible cplgs. are needed at the CMU wall penatration and riser nipply size and lenght has not been indicated on the plans for verification. Other than the exterior canopy inspection tomorrow, per Mark and I's dicussion the remaining building will be scheduled for monday.