INSP-Final Inspection | 4/11/2013 | 4/12/2013 | 4/12/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | FAIL |
Troy Cobbley
|
|
|
Forward flush passed inspection but can not final until the latest plans have been provided.
|
INSP-Final Inspection | 4/8/2013 | 4/9/2013 | 4/9/2013 | A | FAIL |
Troy Cobbley
|
|
|
The forward flush test failed and the plan modifications are not on site.
|
INSP-Sprinkler Rough-in | 4/2/2013 | 4/3/2013 | 4/3/2013 | A | PASS |
Troy Cobbley
|
|
|
The 24hr air test on the dry system passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2013 | 4/2/2013 | 4/2/2013 | P | PASS |
Troy Cobbley
|
|
|
The oh hydro of the 4" riser/steim passed. The 24 hour air test of the dry system was startedat 12:00 with 44psi on the guage. Previous correction items in the shop areas have been corrected.
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2013 | 3/29/2013 | 3/29/2013 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic testing of the new dry system, 6" riser, and FDC completed satisfactory.
|
INSP-Sprinkler Rough-in | 3/18/2013 | 3/19/2013 | 3/19/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" where piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2013 | 3/15/2013 | 3/15/2013 | A | PASS |
Troy Cobbley
|
|
|
Under ground hydro test passed.
|
INSP-Sprinkler Rough-in | 3/6/2013 | 3/7/2013 | 3/7/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" where sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2013 | 2/21/2013 | 2/21/2013 | A | PART |
Forrest France
|
|
|
Mark J is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/20/2013 | 2/20/2013 | 2/20/2013 | P | PART |
Troy Cobbley
|
|
|
The original "job site copy" of plans with review notes and data sheets needs to be on site at the next inspection. I gave the ok to cover on the west side exterior canopy. The south and east canopy have been covered without any piping inspection. The contractor is now removing plywood for an inspection to be scheduled for tomorrow. I spoke to Odie, with Steed Const. about covering prior to rough-in inspections. I did look at one interor area, marked in red on the plans, and noted three items. One is a retaining strap needs installed correctly, the other is flexible cplgs. are needed at the CMU wall penatration and riser nipply size and lenght has not been indicated on the plans for verification. Other than the exterior canopy inspection tomorrow, per Mark and I's dicussion the remaining building will be scheduled for monday.
|