INSP-Final Inspection | 1/7/2013 | 1/7/2013 | 1/7/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 1/3/2013 | 1/4/2013 | 1/4/2013 | P | FAIL |
Troy Cobbley
|
|
|
Need the spare heads/wrench for the head box and the backflow certified.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2012 | 12/7/2012 | 12/7/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic re-test passed for both the first and second floors.
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2012 | 12/5/2012 | 12/5/2012 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Lonnie phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2012 | 12/4/2012 | 12/4/2012 | P | NR |
Forrest France
|
|
|
Guages below 200 psi. @ approx 190.
|
INSP-Sprinkler Rough-in/Hydro | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed on both systems due to visable pressure loss.
|
INSP-Sprinkler Rough-in | 11/1/2012 | 11/1/2012 | 11/2/2012 | P | PASS |
Troy Cobbley
|
|
|
Tenting is complete. Piping is ok to cover.
|
INSP-Sprinkler Rough-in | 10/29/2012 | 10/29/2012 | 10/29/2012 | P | PART |
Forrest France
|
|
|
Overhead rough-in inspection completed. Need to verify lintel or door at second floor bathroom to meet ft2 exception or install a pendent, missing sprinkler heads at two locations. Tenting to be inspected prior to approval for cover.
|