INSP-Final Inspection | 9/3/2013 | 9/4/2013 | 9/4/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/29/2013 | 8/30/2013 | 8/30/2013 | A | CANC |
Troy Cobbley
|
|
|
Please call Perly 30 minutes prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2013 | 8/28/2013 | 8/28/2013 | P | PASS |
Troy Cobbley
|
|
|
OH Hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 8/27/2013 | 8/27/2013 | 8/27/2013 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed due to visible pressure loss on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2013 | 8/26/2013 | 8/26/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in | 8/16/2013 | 8/19/2013 | 8/19/2013 | A | PART |
Troy Cobbley
|
|
|
Piping can be covered but several locations marked in red have upright sprinkler coverage overspaced due to insulation. Also several of the classroom closets have surface mounted light fixtures located right next to sprinkler heads. Ceiling tile will need to be removed to verify these corrections.
|
INSP-Sprinkler Rough-in | 5/28/2013 | 5/28/2013 | 5/28/2013 | P | PASS |
Troy Cobbley
|
|
|
The underground flush passed. Not ready for an additional cover inspection.
|
INSP-Sprinkler Rough-in | 5/8/2013 | 5/9/2013 | 5/9/2013 | A | PASS |
Troy Cobbley
|
|
|
Hard lids ok to cover. I noed one location in the northwest corner of the building where upright sprinkler coverage is needed above one of the hardlids.
|
FIR-Aging Inspection | 3/15/2013 | 3/15/2013 | 3/15/2013 | | NR |
Troy Cobbley
|
|
|
work is in progress
|