INSP-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 1/16/2013 | 1/17/2013 | 1/17/2013 | P | FAIL |
Troy Cobbley
|
|
|
The audible notification devices are not synchronized as required per NFPA 72 18.4.2.5 . The tenant area new devices do not sync with the existing area corridor devices.
|
INSP-Final Inspection | 1/15/2013 | 1/16/2013 | 1/16/2013 | P | CANC |
Troy Cobbley
|
|
|
Cancel per tim Phone #: ###-####
|
INSP-Final Inspection | 1/8/2013 | 1/8/2013 | 1/8/2013 | P | FAIL |
Troy Cobbley
|
|
|
The new 15cd strobe in the corridor is overspaced. Also notification needs to be extended into the corridor in front of the restrooms since the door that is shown on the building plans has not been installed. No testing was actually performed. All other spacing within the tenant space appears ok. Tim and I discussed options.
|