Information based on query as of Thursday, May 16, 2024.
Permit Information
Permit NumberFIR13-00011
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 800 W MAIN ST
Project Name8th and Main Tower Core and Sh
Customer Number 
ePlanReviewYes
Description
Core and shell submittal for the 3rd through 15th floors. 3rd, 4th and 5th floors area parking grages protected with 3 looped dry systems fed from a dry system manifold in the basement. 6th through the 15th floors are typical office lease space floors protected with a gridded wet system fed from the 6" standpipe in stair #1.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/7/20141/10/20141/10/2014APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Sprinkler Rough-in/Hydro1/6/20141/6/20141/6/2014APART
DetailsForrest France
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Final Inspection12/17/201312/17/201312/18/2013PPART
DetailsForrest France
Final pending trip times at dry systems floor levels 3, 4, and 5 per plan review notes item #2 and alternate agreement letter.
INSP-Final Inspection12/12/201312/13/201312/13/2013APART
DetailsForrest France
Refer to fire plan review note # 2 regarding alternate agreement for trip times at the dry systems. C/N items noted at floors 7,8,9, and 12..
INSP-Final Inspection11/27/201312/2/201312/3/2013APART
DetailsForrest France
Completed trip testing for new dry systems at the 3rd, 4th, and 5th floor parking garage levels. Also noted obstructed upright coverage at the service elevator lobbies typical most floors 6-15, missing hangers on mains parallel to and beneath stairways, temporary construction office at the NE corner of the 10th floor disrupts shell coverage. Final shell walkthrough incomplete at this time.
INSP-Final Inspection11/19/201311/22/201311/26/2013ANR
DetailsForrest France
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Conference7/1/20137/1/20137/1/2013PDONE
DetailsForrest France
Regarding upright coverage at the mechanical penthouse.
INSP-Sprinkler Rough-in/Hydro4/24/20134/25/20135/2/2013PPART
DetailsForrest France
Overhead hydrostatic test at floors 11 -15 completed acceptable.
INSP-Sprinkler Rough-in/Hydro4/8/20134/8/20134/12/2013PPART
DetailsForrest France
INSP-Sprinkler Rough-in4/3/20134/3/20134/3/2013PPART
DetailsForrest France
Regarding noted C/N items
INSP-Sprinkler Rough-in/Hydro3/27/20133/29/20133/29/2013PPART
DetailsForrest France
OH hydrostatic test of the 3rd, 4th, and 5th floor dry systems completed satisfactory. Also finished hydrostatic tests of shell system work at the 6th -10th floor levels.
INSP-Sprinkler Rough-in3/20/20133/21/20133/22/2013APART
DetailsForrest France
Shell work at the 9th, 10th, and 11th floors inspected today- noted items include overspaced head at the 9th floor restroom, ssu at south duct needs adjustment, missing hangers at 11th floor arm-overs.
INSP-Sprinkler Rough-in3/18/20133/18/20133/21/2013PPART
DetailsForrest France
INSP-Sprinkler Rough-in3/14/20133/15/20133/15/2013APART
DetailsForrest France
Completed shell fire protection rough-in at floors 7 and 8. Noted missing hangers at floor 8, beam obstruction at the fire service elevator lobby typical per floor.
INSP-Sprinkler Rough-in3/13/20133/14/20133/14/2013PPART
DetailsForrest France
6th floor rough-in completed. Noted missing coverage at the SE corner, beam obstruction at the fire service elevator lobby.
INSP-Sprinkler Rough-in3/6/20133/8/20133/13/2013APART
DetailsForrest France
Refer to stamped plan set regarding 3rd floor rough-in correction items including spacing, obstructions, field changes, incompleted piping due to construction underway, hangers, coverage at the electrical room.
INSP-Final Inspection1/2/20141/2/2014 P 
DetailsForrest France
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in3/11/20133/12/2013 P 
DetailsForrest France
This is for the 3rd, 4th & 5th Fl. Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus