INSP-Final Inspection | 9/9/2013 | 9/10/2013 | 9/11/2013 | A | PASS |
Forrest France
|
|
|
Forward flow testing completed satisfactory.
|
INSP-Final Inspection | 9/6/2013 | 9/9/2013 | 9/9/2013 | P | DEFR |
Forrest France
|
|
|
Please call 1/2 hr prior to inspection. Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 9/5/2013 | 9/6/2013 | 9/6/2013 | P | FAIL |
Troy Cobbley
|
|
|
Need forward flush to final.
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 8/9/2013 | 8/12/2013 | 8/12/2013 | A | FAIL |
Troy Cobbley
|
|
|
Hydro test failed due to a visible drop in pressure at the guage. Also sprinkler coverage has not been installed under an overhead door. This work will need to be done prior to a hydro test.
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2013 | 8/9/2013 | 8/9/2013 | P | NR |
Forrest France
|
|
|
Hydrostatic test incompleted due to system leakage in need of repair.
|
INSP-Sprinkler Rough-in | 8/2/2013 | 8/5/2013 | 8/5/2013 | A | PART |
Troy Cobbley
|
|
|
The retail area ceilings are ok to cover piping. I noted one location where pendant mount lighting is blocking the pendant sprinkler heads. The three time rule of NFPA 13 chapter 8 should apply.
|
INSP-Sprinkler Rough-in | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | PASS |
Troy Cobbley
|
|
|
Todays inspection was to verify that the insulation had been repaired at the deck and was no longer obstructing the upright sprinkler heads. All areas had been repaired except for three locations. I will verify these three at the next rough-in inspection.
|
INSP-Sprinkler Rough-in | 7/3/2013 | 7/5/2013 | 7/5/2013 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the hangers and piping which passed except Nate is going to add two branchline restraints for me. A separate inspection will be needed for approval to cover. As of today insulation is blocking the upright sprinkler coverage in many locations and the ceiling "t bar" has not been installed yet to verify actual pendant head layout.
|
INSP-Sprinkler Rough-in | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Nate
|
INSP-Sprinkler Rough-in | 6/18/2013 | 6/19/2013 | 6/19/2013 | P | PART |
Forrest France
|
|
|
Okay to cover ceilings at the mens, womens, family and pharmacy restrooms as marked and dated on stamped plans. Discussed coverage at the coolers, UG fire supply flush post demo.
|
INSP-Sprinkler Rough-in | 6/14/2013 | 6/17/2013 | 6/17/2013 | A | PART |
Forrest France
|
|
|
Overhead work okay to cover at the cash room and entry vestibule.
|
INSP-Sprinkler Rough-in | 6/13/2013 | 6/14/2013 | 6/14/2013 | P | FAIL |
Forrest France
|
|
|
Inspection for sheetrock ceiling cover at the cart storage and cash rooms only- Draft stop above the cart storage area ceiling creates an obstruction to upright sprinkler coverage, noted mixed temp. heads are installed at the cart storage room absent of a specific heat source, missing approved plans on site.
|