INSP-Final Inspection | 11/7/2013 | 11/7/2013 | 11/7/2013 | P | PASS |
Forrest France
|
|
|
Verified points map has been posted, recieved record of completion forms. Fire alarm permit finaled.
|
INSP-Alarm Testing | 8/29/2013 | 9/4/2013 | 9/5/2013 | P | PART |
Forrest France
|
|
|
Completed remainder of functional testing including occupant notification, EOL, descriptors for the second floor initiating devices, ADA room coverage. One HS repaired while on site. Final pending points map to be posted at the panel per agreement.
|
INSP-Final Inspection | 8/28/2013 | 8/29/2013 | 8/29/2013 | A | PART |
Forrest France
|
|
|
Items tested today include all MP stations, SD at the common, public and employee work areas on both the first and second floors, riser supervision, elevator recall and machine room functions, RA. Verified previous correction items are finished with the exception of a points map at the panel and ADA room coverage. Need to provide descriptors for all second floor initiating devices. Notification testing to be scheduled in advance as discussed with contractor and building manager on site.
|
INSP-Final Inspection | 8/26/2013 | 8/27/2013 | 8/27/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. I spoke to ray about rescheduling. Phone #: ###-####
|
INSP-Final Inspection | 8/6/2013 | 8/9/2013 | 8/9/2013 | A | FAIL |
Forrest France
|
|
|
Completed initial walkthrough. Items noted include; provide a MP at stairway #2 second floor exit door, visual notification at ADA rooms to meet guidelines per NFPA 72 table 18.5.4.6.2, adjust cd settings at notification appliances in mech. room 130 and facilities room 137, post signage at the door leading to the FACP per review note #25, post points map including location of the CO detectors, relocate HD at the elevator machine room, provide for shunt trip and include revision on operations matrix. Functional testing pending corrections and adjustments.
|
FIR-Aging Inspection | 8/6/2013 | 8/9/2013 | 8/9/2013 | A | DONE |
Forrest France
|
|
|
Duplicate inspection request
|
INSP-Conference | 7/9/2013 | 7/9/2013 | 7/9/2013 | P | DONE |
Forrest France
|
|
|
Regarding project completion to date
|
INSP-Alarm Testing | 7/2/2013 | 7/3/2013 | 7/3/2013 | P | NR |
Forrest France
|
|
|
On site visit to determine status of work in progress- FACP and NAC's installed, occupant notification verified at the first and second floors, offsite monitoring included. Noted missing MP at the 2nd floor stairway #2. Project not in condition for final acceptance testing at this time.
|