INSP-Final Inspection | 11/15/2013 | 11/18/2013 | 11/18/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/12/2013 | 11/15/2013 | 11/15/2013 | P | FAIL |
Troy Cobbley
|
|
|
Everything is ok except the alarm bell needs to be relocated to the side of the building where the FDC is located
|
INSP-Sprinkler Rough-in/Hydro | 10/22/2013 | 10/23/2013 | 10/23/2013 | A | PASS |
Troy Cobbley
|
|
|
Second floor hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 10/21/2013 | 10/22/2013 | 10/22/2013 | A | PART |
Troy Cobbley
|
|
|
First floor hydro passed. Second floor failed due to visible leak on the riser.
|
INSP-Sprinkler Rough-in | 10/4/2013 | 10/4/2013 | 10/4/2013 | P | PASS |
Troy Cobbley
|
|
|
Overhead rough-in passed. Piping can be covered. Riser not complete yet. Underground flush passed. FDC is mounted too high and will need to be lowered.
|
INSP-Sprinkler Rough-in | 10/3/2013 | 10/3/2013 | 10/3/2013 | P | CANC |
Troy Cobbley
|
|
|
I noted that the FDC was not located on the street side of the building. So Mike wanted to just reschedule for tomorrow.
|
INSP-Sprinkler Rough-in | 8/12/2013 | 8/14/2013 | 8/14/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover. Its 2" poly like all of the others.
|