INSP-Final Inspection | 10/25/2013 | 10/25/2013 | 10/25/2013 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit okayed for final.
|
INSP-Supply line flush | 10/24/2013 | 10/25/2013 | 10/25/2013 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2013 | 10/4/2013 | 10/4/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Final Inspection | 10/2/2013 | 10/3/2013 | 10/3/2013 | A | PASS |
Troy Cobbley
|
|
|
IBR cover inspection passed
|
INSP-Sprinkler Rough-in | 10/2/2013 | 10/2/2013 | 10/2/2013 | P | PASS |
Troy Cobbley
|
|
|
Remaining underground supply line piping is ok for cover except for the IBR (need to see thrust block).
|
INSP-Sprinkler Rough-in | 10/1/2013 | 10/1/2013 | 10/1/2013 | P | PART |
Troy Cobbley
|
|
|
The underground supply line from the street to the first fitting is ok to cover.
|