Permit Information
Permit NumberFIR13-00704
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 1075 E PARK BLVD
Project NameBSU Classrooms/Old IF&G
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of 6” underground with a yard PIV to a 6” backflow preventer through a 6” riser to a 3” feed main supplying a 3”x2½”x1¼” grid.

Underground is under permit FIR13-00315

A fire sprinkler system will be installed throughout this building in conjunction with this permit and will be used in lieu of rated corridors and to allow unprotected openings in the West exterior wall. To remodel an 11,830 square foot area within an existing 23,200 square foot one story building for a new classroom tenant space for students above the 12th grade. Work is to include interior nonbearing walls, 2 multi-user restrooms accessible to the disabled, an exterior concrete ramp accessible to the disabled, and platforms for new roof top HVAC units. Three new roof top HVAC units will be provided. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The entire building will have a fire sprinkler system installed in conjunction with this permit. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Since combustible materials are exposed within the attic space, the attic is required to have fire sprinkler protection. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/26/20143/27/20143/27/2014APASS
DetailsForrest France
Functional testing and final inspection passed. Previous C/N items finished. Fire sprinkler permit finaled.
INSP-Final Inspection3/26/20143/26/20143/26/2014PDEFR
DetailsForrest France
Scheduled in conjunction with related permit finals 3/27.
INSP-Final Inspection3/24/20143/25/20143/25/2014ANR
DetailsForrest France
Missing riser finish pack including calc stickers, DCVA certification, caps at FDC, sign at outside bell, riser tag, etc., need to complete forward flow, missing escutcheons.
INSP-Sprinkler Rough-in3/6/20143/6/20143/6/2014PPART
DetailsForrest France
Overhead work at the grid ceiling areas completed to date okay for cover. Flex heads at some locations are not perpendicular to the ceiling and will need adjustment.
INSP-Sprinkler Rough-in/Hydro2/13/20142/14/20142/14/2014APART
DetailsForrest France
Overhead hydrostatic testing passed. Noted spacing adjustments will be necessary at the east side offices and classrooms.
INSP-Sprinkler Rough-in1/27/20141/27/20141/27/2014PPART
DetailsForrest France
UG fire supply line and post indicator including stub-in approved for cover.