INSP-Final Inspection | 7/15/2014 | 7/16/2014 | 7/17/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/14/2014 | 7/15/2014 | 7/15/2014 | P | FAIL |
Troy Cobbley
|
|
|
Provide all ot the signs/tags/stickers for the final
|
INSP-Final Inspection | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Roy. Will reschedule for tomorrow
|
INSP-Sprinkler Rough-in/Hydro | 4/18/2014 | 4/21/2014 | 4/21/2014 | A | PART |
Forrest France
|
|
|
Completed hydrostatic testing for both buildings floors 1, 2 and 3. Hydro at the north building 2nd floor failed due to pressure loss at the guage and visible leakage in unit 201. Also noted visible leakage at both buidling riser backflow manifolds- N. bldg upstream of the DCVA , S. bld at the #2 DCVA shutoff. Remainder of floor levels passed OH hydro.
|
INSP-Sprinkler Rough-in/Hydro | 4/18/2014 | 4/18/2014 | 4/18/2014 | P | CANC |
Forrest France
|
|
|
Please call Nick 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 4/15/2014 | 4/16/2014 | 4/16/2014 | A | PART |
Forrest France
|
|
|
Completed inspection for tenting and insulation at the south building third floor- Okay to cover after adjustments to one area above the kitchen in the north end unit.
|
INSP-Sprinkler Rough-in | 4/10/2014 | 4/11/2014 | 4/11/2014 | A | PART |
Forrest France
|
|
|
South building 1st and 2nd floor overhead rough-in okayed for cover. One missing hanger added while on site, need to provide matched temp SW heads in the common stairways, patio SW heads to match plan submittals. Third floor cover approval pending tenting and insulation.
|
INSP-Sprinkler Rough-in | 4/2/2014 | 4/3/2014 | 4/3/2014 | P | PART |
Forrest France
|
|
|
Verified tenting and insulation at the third floor. Need adjustment above pendent head in the east end unit bedroom as discussed. Remainder okayed for cover.
|
INSP-Sprinkler Rough-in | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | PART |
Forrest France
|
|
|
Please schedule a rough for 2nd and 3ed floors. Call Nick 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt
|
INSP-Sprinkler Rough-in | 3/24/2014 | 3/24/2014 | 3/24/2014 | P | NR |
Forrest France
|
|
|
Please call Nick 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt
|
INSP-Sprinkler Rough-in | 3/19/2014 | 3/19/2014 | 3/19/2014 | P | PART |
Forrest France
|
|
|
Verified corrections and adjustments at the first floor only. Overspaced hangers at two locations not yet complete. Noted possible light fixture obstructions due to proximity of junction boxes to heads at some locations-
|
INSP-Sprinkler Rough-in | 3/17/2014 | 3/18/2014 | 3/18/2014 | A | FAIL |
Forrest France
|
|
|
First floor corrections include; missing hangers at two locations, piping to SW heads incompleted, provide intermediate temp heads at the furnace closets, min. distance between heads is not met at two units, a swing joint at the west end unit appears to be "dry fit".
|
INSP-Sprinkler Rough-in | 3/13/2014 | 3/13/2014 | 3/13/2014 | A | NR |
Forrest France
|
|
|
Items noted include missing SW heads per plan at the stair enclosures, need intermediate temp heads in the furnace closets, min. distance from ceiling fans at some rooms are not met.
|