INSP-Final Inspection | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | PASS |
Forrest France
|
|
|
Walkthrough passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/3/2014 | 7/7/2014 | 7/7/2014 | A | PART |
Forrest France
|
|
|
Verified added coverage at the exposed 2" CPVC main in the shell area.
|
INSP-Final Inspection | 7/3/2014 | 7/3/2014 | 7/3/2014 | P | PART |
Forrest France
|
|
|
Completed walkthrough of finishes at the 3rd floor core scope of work. Need to add fire sprinkler protection for exposed 2" CPVC main at tie-in to apartment system.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2014 | 5/6/2014 | 5/6/2014 | A | PART |
Forrest France
|
|
|
Third floor corridor and electrical room as clouded and dated on approved plans okayed for ceiling cover. Preliminary walkthrough of the some areas at the 2nd floor east side OTS and sheetrock lid locations. Discussed FDC and test header locations facing 11th street.
|
INSP-Sprinkler Rough-in | 4/17/2014 | 4/18/2014 | 4/18/2014 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler rough-in at the 3rd floor restrooms, vestibules, storage room and two sheetrock lid ceilings in the common corridor per dated notes okayed for cover.
|
INSP-Sprinkler Rough-in | 4/17/2014 | 4/17/2014 | 4/17/2014 | P | CANC |
Forrest France
|
|
|
Terry Nelson Phone #: ###-#### - - terry called in and canceled and reschuled for tomorrow morning /// 4-17-14 ps
|
INSP-Sprinkler Rough-in | 3/4/2014 | 3/4/2014 | 3/4/2014 | P | PART |
Forrest France
|
|
|
Okay to cover sheetrock ceilings at the 3rd floor elevator lobby- ref. dated annotations on approved plans.
|