Permit Information
Permit NumberFIR14-00222
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7211 W COLONIAL ST
Project NameABU Games Retrofit
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of approximately 4”x205’ C-900 underground piping, fittings an thrust blocks. This is one 4” system with backflow preventer protecting the entire building consisting of a roof and mezzanine. The building is primarily Light hazard with the receiving and mercantile area protected as Ordinary Hazard II. The entire area is gridded with 3” mains and 1 ¼”, 1 ½” branch lines. The mezzanine runs the length of building in the center of the building.
There does not appear to be a building permit at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/30/201410/31/201410/30/2014APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection10/30/201410/30/201410/30/2014PCANC
DetailsForrest France
Please call when you are on your way Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Final Inspection10/21/201410/21/201410/21/2014PNR
DetailsForrest France
Pending project related fire alarm work.
INSP-Final Inspection10/20/201410/21/201410/21/2014ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Supply line flush10/13/201410/14/201410/14/2014APASS
DetailsTroy Cobbley
Forward flow test passed
INSP-Sprinkler Rough-in/Hydro10/7/201410/7/201410/7/2014PPASS
DetailsTroy Cobbley
Overhead hydro test passed on the second try.
INSP-Sprinkler Rough-in/Hydro10/2/201410/3/201410/3/2014PCANC
DetailsTroy Cobbley
Was to be an underground hydro. Canceled due to pressure loss.
INSP-Supply line flush10/2/201410/3/201410/3/2014APASS
DetailsTroy Cobbley
Underground flush passed
INSP-Sprinkler Rough-in10/1/201410/1/201410/1/2014PPASS
DetailsTroy Cobbley
Verified combustible concealed spaces are filled with insulation. Will need verification that the insulation is non-combustible. Also verified three added dry uprights to provide additiional protection where heads were previously overspaced.
INSP-Sprinkler Rough-in9/29/20149/30/20149/30/2014PCANC
DetailsTroy Cobbley
Finished rough-in inspection at the morning inspection request.
INSP-Sprinkler Rough-in9/29/20149/30/20149/30/2014APASS
DetailsTroy Cobbley
Remaining rough-in passed. Riser room/piping not built/installed yet.
INSP-Sprinkler Rough-in9/26/20149/29/20149/29/2014PCANC
DetailsTroy Cobbley
Performed a rough-in inspection this morning. No time for second visit today.
INSP-Sprinkler Rough-in9/26/20149/29/20149/29/2014APART
DetailsTroy Cobbley
See the city approved plans for locations where the rough-in inspection has passed. i noted three dry uprights that appear to be overspaced.
INSP-Supply line flush7/14/20147/14/20147/14/2014PPASS
DetailsTroy Cobbley
Inspection was not for a flush but for the underground supply hydro test. The hydro test passed.
INSP-Supply line flush7/14/20147/14/20147/14/2014AFAIL
DetailsTroy Cobbley
Inspection requested via web by Anthony Minichiello

No contact phone number so I went to the project site and was unable to contact the sprinkler contractor and there is no pressure on the underground supply piping.
INSP-Supply line flush7/11/20147/11/20147/11/2014PCANC
DetailsTroy Cobbley
Cancel per Anthony Minichiello
INSP-Supply line flush7/10/20147/10/20147/10/2014PPASS
DetailsTroy Cobbley
Inspection was not for a flush but for a cover inspection of the underground supply. The cover inspection passed and the pipe can be buried.
INSP-Supply line flush7/8/20147/9/20147/9/2014APART
DetailsTroy Cobbley
Verified depth of bury and size is correct. No thrust blocks installed yet.
INSP-Supply line flush6/26/20146/30/20146/30/2014PFAIL
DetailsTroy Cobbley
Underground supply piping was not ready for inspection. Anthony and I discussed sprinkler protection in the concealed spaced.
INSP-Sprinkler Rough-in6/26/20146/27/20146/27/2014PDONE
DetailsTroy Cobbley
Inspection was part rough-in and part conference. The dry sprig ups, per conversation with Anthony, are too far from the deck but it appears that Anthony has a solution. I started the rough-in inspection for the piping under the mezzanine but stopped after finding pipe re-routing, elevation changes and alot of additional fittings. Also the "interstitial" space above the first floor ceiling and the second floor is a combustible concealed space with no sprinkler protection. After finding these items I determined that a plan modification will be needed so I stopped inspecting this area. I continued with the upper level piping and found for the most part the rough-in is passed but 25% of the piping has not been instlled yet as well as all of the branchline seimic bracing and earthquake bracing has not been installed yet. There has also been minor pipe routing changes and additional fittings here as well. I also found atleast one flat face bushing being used to reduce a 1 1/2" pipe to 1 1/4".

Per Anthony and I's conversation today, I will be requested to come back out after the plan modifications are approved for a re-inspection.
INSP-Sprinkler Rough-in6/26/20146/27/20146/26/2014PCANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello