INSP-Final Inspection | 9/9/2015 | 9/11/2015 | 9/11/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2015 | 8/19/2015 | 8/19/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2015 | 8/13/2015 | 8/13/2015 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed due to visible loss at guage.
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 7/29/2015 | 7/30/2015 | 7/30/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting passed. Piping can be covered. Brian and I spoke about the tenting to create a pocket for the piping since in several places the tenting contractor stapled the insulation to the deck. He was going to follow up with Anderson Construction.
|
INSP-Supply line flush | 7/28/2015 | 7/29/2015 | 7/29/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 7/27/2015 | 7/28/2015 | 7/28/2015 | P | CANC |
Troy Cobbley
|
|
|
And tenting Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 6/16/2015 | 6/16/2015 | 6/16/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground Supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 6/4/2015 | 6/5/2015 | 6/5/2015 | P | FAIL |
Jim Page
|
|
|
Underground piping stub in did not match city approved drawings.
|
INSP-Sprinkler Rough-in | 6/4/2015 | 6/4/2015 | 6/4/2015 | P | FAIL |
Troy Cobbley
|
|
|
I called the contact three times and left one message. Went to project site and did not find the contact. No inspection performed.
|