INSP-Final Inspection | 9/9/2015 | 9/10/2015 | 9/10/2015 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2015 | 8/19/2015 | 8/19/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2015 | 8/13/2015 | 8/13/2015 | P | FAIL |
Troy Cobbley
|
|
|
Above ground hydro test failed due to visible loss at guage
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Supply line flush | 7/28/2015 | 7/29/2015 | 7/29/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 7/27/2015 | 7/28/2015 | 7/28/2015 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in and tenting inspection passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 6/10/2015 | 6/10/2015 | 6/10/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground rough to cover passed. Piping can be covered
|
INSP-Sprinkler Rough-in | 6/4/2015 | 6/5/2015 | 6/5/2015 | P | FAIL |
Jim Page
|
|
|
Underground piping stub in did not match city approved drawings.
|
INSP-Sprinkler Rough-in | 6/4/2015 | 6/4/2015 | 6/4/2015 | P | FAIL |
Troy Cobbley
|
|
|
Called contact three times and left one message. Went to job site and did not find contact. No inspection performed.
|