INSP-Final Inspection | 8/5/2015 | 8/6/2015 | 8/6/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 7/27/2015 | 7/28/2015 | 7/28/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 7/22/2015 | 7/23/2015 | 7/23/2015 | P | FAIL |
Troy Cobbley
|
|
|
Stopped at job site and found that the pressure guage is at 185 psi which is below the required 200psi
|
INSP-Sprinkler Rough-in/Hydro | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | FAIL |
Troy Cobbley
|
|
|
The overhead hydro failed due to visible loss on the guage. I also noted that in the northwest corner a wall is going to block coverage of an upright head into the small room just off the corridor.
|
INSP-Sprinkler Rough-in/Hydro | 7/9/2015 | 7/10/2015 | 7/10/2015 | P | CANC |
Troy Cobbley
|
|
|
Was to be an overhead hydro. I stopped at the project site and found a puddle on the floor from a leaking fitting. I let Richard know. Will be rescheduled for later.
|
INSP-Sprinkler Rough-in | 6/19/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Troy Cobbley
|
|
|
Overhead rough in inspection passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2015 | 6/22/2015 | 6/22/2015 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro inspection failed due to puddles on the floor and I will need the pendant heads cut in prior to a hydro test.
|