Permit Information
Permit NumberFIR15-00504
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 3494 S TK AVE
Project NameB&D FOODS NEW TEST KITCHEN
Customer Number 
ePlanReviewYes
Description
[B & D Foods - Culinary Center] - Quick Permit
OWNER IS BUILING A SMALL MEZZ AND CREATING A TEST KITCHEN BELOW.

(B&D FOODS)(CULINARY CENTER)Minor construction within existing warehouse, adding (3) walls and ceiling structure to enclose a new kitchen area. Area above kitchen designed for light weight storage, accessed by ships ladder with guard rails. Scope of work to include opening in existing exterior wall for hood termination, MAU unit outside of building with CMU screen. Special inspection required per engineer. Structural calculations included for the storage mezzanine. Plumbing, mechanical and electrical as noted on plans. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department.**ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/18/20159/21/20159/21/2015APASS
DetailsJim Page
Previously noted items addressed, combustable pocket above commercial hood sheet-rocked, taped and fire caulked, no need for additional fire sprinklers above commercia hood. Final fire sprinkler system inspection passed/complete.
INSP-Final Inspection9/15/20159/15/20159/15/2015PFAIL
DetailsJim Page
Space above commercial hood not protected, exposed combustible material in pocket, needs fire sprinkler heads installed to protect area.
INSP-Final Inspection9/11/20159/14/20159/14/2015AFAIL
DetailsThomas Walsh
Two (2) sprinklers obstructed - one by surface mounted light fixture, and the other installed too close (within 3 in") of kitchen hood. Contractor agreed to address these discrepancies and call back for another final inspection.
INSP-Sprinkler Rough-in/Hydro7/30/20157/30/20157/30/2015PPASS
DetailsTroy Cobbley
Combustible concealed space has been filled with insulation. Piping can be covered. Also the earthquake bracing has been completed.
INSP-Sprinkler Rough-in7/29/20157/29/20157/29/2015PPASS
DetailsTroy Cobbley
Rough-in passed. Earth quake bracing has not been installed yet but will be verified at next rough-in when I verify the combustible concealed space has been filled with insulation. Sheet rock can not be installed yet.