INSP-Final Inspection | 9/18/2015 | 9/21/2015 | 9/21/2015 | A | PASS |
Jim Page
|
|
|
Previously noted items addressed, combustable pocket above commercial hood sheet-rocked, taped and fire caulked, no need for additional fire sprinklers above commercia hood. Final fire sprinkler system inspection passed/complete.
|
INSP-Final Inspection | 9/15/2015 | 9/15/2015 | 9/15/2015 | P | FAIL |
Jim Page
|
|
|
Space above commercial hood not protected, exposed combustible material in pocket, needs fire sprinkler heads installed to protect area.
|
INSP-Final Inspection | 9/11/2015 | 9/14/2015 | 9/14/2015 | A | FAIL |
Thomas Walsh
|
|
|
Two (2) sprinklers obstructed - one by surface mounted light fixture, and the other installed too close (within 3 in") of kitchen hood. Contractor agreed to address these discrepancies and call back for another final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2015 | 7/30/2015 | 7/30/2015 | P | PASS |
Troy Cobbley
|
|
|
Combustible concealed space has been filled with insulation. Piping can be covered. Also the earthquake bracing has been completed.
|
INSP-Sprinkler Rough-in | 7/29/2015 | 7/29/2015 | 7/29/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Earth quake bracing has not been installed yet but will be verified at next rough-in when I verify the combustible concealed space has been filled with insulation. Sheet rock can not be installed yet.
|