Information based on query as of Sunday, June 2, 2024.
Permit Information
Permit NumberFIR16-00284
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 2967 W CRESCENT RIM DR
Project NameCrescent Rim Bldg #4
Customer Number 
ePlanReviewYes
Description
[Crescent Rim #4 - Garage]
The fire sprinkler scope of work consists of four levels of protection. There is a 2-hour separation between the first level and second level. The first level is a heated parking garage protected per NFPA 13 as a wet system. Levels 2-4 is a residential area protected per NFPA 13R except for part of the second level which has a dry system protecting a parking canopy. There are two wet manual standpipes with isolation valves.

The underground piping is under permit FIR16-00183

CRESCENT RIM RESIDENTIAL CONDOMINIUM BUILDING #4 – THREE STORIES ABOVE EXISTING GARAGE – DRH05-00397 AND CUP04-00107) (4-6-16 PLAN MODIFICATION TO REVISE “STAIRWAY L” TO ELIMINATE A FLOOR CANTILEVER OF ABOUT ONE FOOT ON ALL LEVELS ABOVE THE BASEMENT. WORK ALSO INCLUDES OTHER MINOR STRUCTURAL ADJUSTMENTS.) (3-9-16 PLAN MODIFICATION TO CHANGE THE UNIT NUMBERS FOR THE DWELLING UNITS, INCREASE WINDOW ENERGY EFFICIENCY, DECREASE THE ROOF ENERGY EFFICIENCY, MODIFY THE EXTERIOR LIGHTING CONTROLS, AND TO MAKE OTHER MINOR CHANGES. CJW) (3-10-16 BEFORE ROUGH INSPECTIONS FOR THE 3 STORY APARTMENT BUILDING ARE APPROVED, A LETTER IS REQUIRED TO BE SUBMITTED FROM THE ENGINEER OF RECORD VALIDATING THAT THE PODIUM HAS NOT EXPERIENCED SIGNIFICANT DEGRADATION OR DAMAGE SINCE IT WAS CONSTRUCTED. IF REPAIRS ARE REQUIRED, COMPLETE DESIGNS AND DRAWINGS ARE REQUIRED TO BE SUBMITTED TO SHOW HOW THE REPAIRS WILL BE DONE. REPAIRS SHALL NOT BE COMMENCED UNTIL THE DRAWINGS FOR THE PROPOSED REPAIRS ARE REVIEWED AND APPROVED. THE 3 STORY APARTMENT BUILDING IS NOT ALLOWED TO BE OCCUPIED UNTIL ALL REPAIRS ARE COMPLETED AND APPROVED. CJW) The NFPA 13-R fire sprinkler system is used for occupancy. This project description replaces all previous descriptions. The work is required to comply with all applicable codes and ordinances in effect on August 14, 2006, the date of permit application. To construct a 3 story, 53,543 square foot residential apartment building (19,822 square feet 1st story, 19,822 square feet 2nd story, and 13,899 square feet 3rd story) on top of an existing 18,661 square foot basement parking garage. The basement was constructed under permit BLD06-02321 (S-2 Occupancy with an occupant load of 93). There will be 19 dwelling units and 1 hotel suite within this building. There will be 2 Type A dwelling units, 17 Type B dwelling units, and 1 accessible hotel suite. The work is to include concrete footings, concrete piers, concrete stem walls, concrete slabs on grade, exterior wood stud bearing walls, interior wood stud bearing walls, wood beams, wood columns, steel beams, steel columns, wood shear walls, wood joist floor systems, wood truss roof systems, wood trellises, synthetic slate roof shingles, mechanically fastened single ply roofing at flat roof areas, roof drains and overflow drains or scuppers at flat roofs, exterior portland cement stucco, exterior manufactured stone veneer, interior 1-hr corridors, interior 2-hr stairway enclosures, a 2-hr elevator shaft, a 1-hr trash chute shaft enclosure with 1-hr trash room, interior doors, exterior doors, exterior windows, gas fireplaces, millwork, and finishes. Special Inspection is required for welding, bolding of steel to steel, wind resistance, seismic resistance, and post installed concrete anchors. Before any holes are drilled through or into the post tensioned concrete deck, the deck is required to be X-rayed, or otherwise scanned (e.g. ground penetrating radar), to precisely determine the location of concrete reinforcement. No concrete reinforcement is allowed to be cut, including post tensioned cables. This requirement applies to holes for anchor bolts, plumbing pipes, electrical conduit, etc. The design for engineered wood trusses is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, with the Structural Engineer’s design, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with N
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/6/201712/7/201712/7/2017APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection10/31/201710/31/201710/31/2017PFAIL
DetailsTroy Cobbley
Provide minor corrections as discussed with the pipe clearance and pipe straps. Need test papers
INSP-Final Inspection10/25/201710/26/201710/26/2017AFAIL
DetailsTroy Cobbley
Not ready for final yet but we did test the dry pipe system and the interconnection with the fire alarm panel. It appears that a rough-in inspection is still needed for the garage.
INSP-Final Inspection10/24/201710/25/201710/25/2017PFAIL
DetailsTroy Cobbley
Not all items tested today due to time constraints. See the on site fire alarm as-built plans for the sprinkler devices tested today as marked "ok".
INSP-Final Inspection10/24/201710/24/201710/24/2017PCANC
DetailsTroy Cobbley
Before 2:00 am or after 3:00 call ahead the elevator guy can’t be here between 2:00 and 3:00. Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Sprinkler Rough-in/Hydro10/19/201710/20/201710/20/2017APASS
DetailsJim Page
24 hour air test complete.
INSP-Sprinkler Rough-in/Hydro10/18/201710/19/201710/19/2017ADONE
DetailsTroy Cobbley
24 hour air test on dry system started at 8:45 with 44psi on the guage.
INSP-Sprinkler Rough-in/Hydro10/18/201710/18/201710/18/2017PPASS
DetailsTroy Cobbley
200 psi Hydro test on dry system passed
INSP-Sprinkler Rough-in/Hydro10/17/201710/17/201710/17/2017PFAIL
DetailsTroy Cobbley
Hydro test of the dry system failed due to visible loss of pressure at the guage.
INSP-Sprinkler Rough-in/Hydro10/12/201710/13/201710/13/2017APASS
DetailsTroy Cobbley
Hydro on first/second/ third floor passed
INSP-Sprinkler Rough-in9/20/20179/21/20179/21/2017APASS
DetailsTroy Cobbley
First and second floor corridor grid ceiling are ok for cover.
INSP-Sprinkler Rough-in9/8/20179/8/20179/8/2017PPASS
DetailsTroy Cobbley
Trash shoots 2nd floor 3rd floor and trash shoot room sprinkler work is complete. Also the sprinkler piping for the 3rd floor Corridor is ok to cover. Suite 106 sprinkler work is complete..
INSP-Sprinkler Rough-in9/1/20179/5/20179/5/2017APASS
DetailsTroy Cobbley
The fire sprinkler work in Suites 203, 204, 205, 206 and 302 is passed. The Closet light in Suite 106 still needs rotated. The Pantry head in Suite 101 has been corrected. I noted that a pendant is painted in Suite 208.
INSP-Sprinkler Rough-in8/31/20179/1/20179/1/2017APART
DetailsTroy Cobbley
Todays walk through was for the first floor apartments. I noted one painted concealer pendant head and on pendant that is blocked by a surface mounted light.
INSP-Sprinkler Rough-in8/2/20178/3/20178/3/2017APASS
DetailsTroy Cobbley
Installed verifed 2 dry flex heads in the breezeway on Ground Level. Piping is ok to cover.
INSP-Sprinkler Rough-in7/6/20177/7/20177/7/2017APASS
DetailsTroy Cobbley
First floor north corridor soffits are ok to cover and the south building Guest Room
INSP-Sprinkler Rough-in7/5/20177/5/20177/5/2017PPASS
DetailsTroy Cobbley
Second floor cover for the soffits is ok for cover in the corridor.
INSP-Sprinkler Rough-in6/26/20176/27/20176/27/2017APASS
DetailsTroy Cobbley
Third floor corridor soffits are ok to cover
INSP-Sprinkler Rough-in5/15/20175/16/20175/16/2017ACANC
DetailsTroy Cobbley
Duplicate inspection
INSP-Sprinkler Rough-in5/15/20175/16/20175/16/2017APASS
DetailsTroy Cobbley
1st and 3rd floor south side corridor soffit heads are ok to cover. I noted one area on both the first and third floors where sprinkler pendants are less than 8' apart which is not allowed for extended coverage heads. I need verification that the heads can be that close or heads need to be relocated.
INSP-Sprinkler Rough-in4/13/20174/14/20174/14/2017APASS
DetailsTroy Cobbley
Unit 107 piping is ok for cover.
INSP-Sprinkler Rough-in4/12/20174/13/20174/13/2017APASS
DetailsTroy Cobbley
Unit 101 sprinkler piping can be covered.
INSP-Sprinkler Rough-in4/5/20174/6/20174/6/2017APASS
DetailsTroy Cobbley
Unit 201 piping above soffits can be covered
INSP-Sprinkler Rough-in/Hydro4/4/20174/5/20174/5/2017APASS
DetailsTroy Cobbley
Hydro test on the standpipes; the parking garage passed. I also did a rough-in on the standpipes and only found one floor clamp missing.
INSP-Sprinkler Rough-in4/4/20174/5/20174/5/2017APASS
DetailsTroy Cobbley
Rough to cover for units 304 and 208 passed. All piping in the apartments can be covered.
INSP-Sprinkler Rough-in3/28/20173/29/20173/29/2017PPASS
DetailsTroy Cobbley
Rough to cover in room 301 passed. All piping can be covered.
INSP-Sprinkler Rough-in3/22/20173/23/20173/23/2017APASS
DetailsTroy Cobbley
Unit 202 soffit piping can be covered. Rough-in passed.
INSP-Sprinkler Rough-in3/14/20173/15/20173/15/2017APASS
DetailsTroy Cobbley
Unit 207 soffit piping passed. Piping can be covered.
INSP-Sprinkler Rough-in3/8/20173/9/20173/9/2017APASS
DetailsTroy Cobbley
Unit 303 soffit piping is ok to cover.
INSP-Sprinkler Rough-in3/3/20173/6/20173/6/2017APASS
DetailsTroy Cobbley
Apartment 302 lower soffits ok to cover.
INSP-Sprinkler Rough-in2/28/20173/1/20173/1/2017APASS
DetailsTroy Cobbley
Rough to cover for unit 102 passed. Piping in soffits can be covered.
INSP-Sprinkler Rough-in2/27/20172/28/20172/28/2017APASS
DetailsTroy Cobbley
The rough to cover on the Dry system is passed. The missing line restraints have been added
INSP-Sprinkler Rough-in2/22/20172/23/20172/23/2017APASS
DetailsTroy Cobbley
Apartment 206 soffit piping is ok to cover and dry system under canopy rough-in passed. Dry piping can be covered except for the areas where branchline restraints need to be installed.
INSP-Sprinkler Rough-in2/22/20172/23/20172/22/2017ACANC
DetailsTroy Cobbley
206 rough in Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Sprinkler Rough-in2/20/20172/21/20172/21/2017APASS
DetailsTroy Cobbley
Unit 203 piping in the soffits is ok to cover.
INSP-Sprinkler Rough-in2/15/20172/16/20172/16/2017APASS
DetailsTroy Cobbley
The pendant head has been added in Apartment 204. Piping can be covered.
INSP-Sprinkler Rough-in2/14/20172/15/20172/15/2017PPART
DetailsTroy Cobbley
Todays inspection was for the piping in the lower soffits which is ok to cover except one head needs to be added in the Living Area. This new pendant will be verified at the next inspection.
INSP-Sprinkler Rough-in2/9/20172/9/20172/9/2017PPASS
DetailsTroy Cobbley
The piping in the lower soffits of apartment 205 is ok to cover.
INSP-Sprinkler Rough-in2/7/20172/8/20172/8/2017PPART
DetailsTroy Cobbley
Todays inspection was for apartment 205, lower soffit piping. Most piping can be covered except in the Kitchen area. There is an issue with coverage in this area that is being worked out prior to a cover approval.
INSP-Sprinkler Rough-in2/1/20172/2/20172/2/2017APASS
DetailsTroy Cobbley
The modified pendant heads raised due to revised ceiling heights in Apartments 104, 105 and 106 are passed.
INSP-Sprinkler Rough-in1/30/20171/31/20171/31/2017APASS
DetailsTroy Cobbley
This was a re-inspection for Apartment 103. The two pendant heads have been fixed.
INSP-Sprinkler Rough-in1/26/20171/27/20171/27/2017PPART
DetailsTroy Cobbley
The sprinkler piping in apartment 103 is ok to cover except in one bedroom as marked on the plans where the pendant is less than 3' to the light fixture and in the Pantry where the pendant has not been dropped yet. Will check at the re-inspection. Apartment 105 issues have been corrected.

Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Sprinkler Rough-in1/19/20171/20/20171/20/2017APART
DetailsTroy Cobbley
Inspection was for Unit 105 (see plans). It appears per the obstruction charts of NFPA13R that two heads will need to be relocated. They have been marked on the plans and will be checked at the next inspection. The piping in this apartment can be covered.
INSP-Sprinkler Rough-in1/12/20171/13/20171/13/2017APART
DetailsKatie Marron
Inspected drops for drop ceiling in two units on first floor. Marked which units on plans.
INSP-Sprinkler Rough-in1/4/20171/4/20171/4/2017APASS
DetailsTroy Cobbley
See the city approved plans for areas marked ok fo rough to cover on 3rd floor and remainder of 2nd floor
INSP-Sprinkler Rough-in12/22/201612/23/201612/23/2016PPASS
DetailsTroy Cobbley
See the city approved plans for specific rooms on the second floor where the rough to cover passed. Tenting deficiencies are noted in one of the apartments and it is not ok for cover
INSP-Sprinkler Rough-in12/7/201612/8/201612/8/2016APART
DetailsTroy Cobbley
The two apartments at the north end of the second floor that had tenting issues are ok to cover. Also the third floor north single apartment is now ok to cover. See the city approved plans for locations marked.
INSP-Sprinkler Rough-in11/28/201611/29/201611/29/2016APART
DetailsTroy Cobbley
Two of the north side, second floor apartments are ok to cover the other two need tenting corrected. Also the north end east side stairwell piping has not been tented yet. See the city approved plans for locations marked.
INSP-Sprinkler Rough-in11/17/201611/18/201611/17/2016ACANC
DetailsTroy Cobbley
Rough to cover on first and second floor North side up to Breezeway Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Sprinkler Rough-in/Hydro11/12/201611/14/201611/14/2016PPART
DetailsTroy Cobbley
Todays inspection was for the sprinkler rough-in for the first and second floors. The rough-in passed on the first floor and the piping in the resident rooms can be covered. However pendant drops have not been installed to the soffits and drop ceilings yet so they will need a re-inspection prior to a complete cover inspection being given. As far as the second floor the basic rough-in passed but piping can not be covered due to tenting not being completed. Again a second inspection will be needed when the soffits and drop ceilings have been installed. I noted that in atleast one location additional fitting had to be added which requires the plans, per a note on the drawings, to be resubmitted for hydraulic calculation verification. Also the second floor plans indicate the balconies are open to above but they actually have partial roofs over them. I spoke to sam and he will follow up with plan review on a plan of action.
INSP-Sprinkler Rough-in/Hydro11/10/201611/14/201611/12/2016ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball