Description |
[Boise Fire Station #4]
The fire sprinkler scope of work consists of protecting a two level fire station with a NFPA 13 system. The system has 6” underground with a 4” riser, backflow preventer and cross mains. The branch lines are 1 ¼” on the first floor and 1 ½” on the second floor.
The underground piping is under permit FIR16-00406
[BLD16-01040] - Permit to construct a new 13,774 square foot fire station. This building is fire sprinklered for area increase and non-separated uses. This building utilizes enhanced lighting to comply with the 2012 IECC / IgCC. Scope of work includes: construction of poured concrete foundation, construction of reinforced CMU exterior walls, construction of new steel bar-joist floor – ceiling framing / steel pan deck, [construction of interior nonbearing walls to create: 10 sleeping units, 8 restrooms / bathing rooms, lobby, two offices, work room, turn out room, decon room, maintenance shop, riser room, SCBA Fill room, 3 storage rooms, laundry room, janitors closet, training classroom, fitness room, and dayroom], new elevator, new electrical, new plumbing, new mechanical, new interior / exterior finishes, new accessible doors / hardware, covered patio on 2nd floor, and related site work. This building is fully fire sprinklered for area increase. **TLW**
|