INSP-Final Inspection | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | FAIL |
Troy Cobbley
|
|
|
The interconnection with the fire alarm panel needs to be retested due to wrong signals from tamper and pressure switches. Also need the forward flush test for 13psi out of the 2 1/2" drain. Need test papers as well
Adam Phone #: ###-####
|
INSP-Sprinkler Rough-in | 7/17/2017 | 7/18/2017 | 7/18/2017 | A | PASS |
Troy Cobbley
|
|
|
The remaining sprinkler piping can be covered. The remaining tenting passed. There are a few can lights that are close to the new pendant sprinklers that I will need verification on.
|
INSP-Conference | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | DONE |
Troy Cobbley
|
|
|
Kitchen area piping is ok to cover.
|
INSP-Conference | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for more locations marked ok where tenting is approved and piping can be covered.
|
INSP-Sprinkler Rough-in | 6/2/2017 | 6/2/2017 | 6/2/2017 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional areas marked "ok" where tenting is passed and piping can be covered.
|
INSP-Sprinkler Rough-in | 5/31/2017 | 6/1/2017 | 6/1/2017 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional areas/rooms where tenting is complete and piping can be covered.
|
INSP-Conference | 5/23/2017 | 5/24/2017 | 5/24/2017 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional rooms where the wet system tenting inspection is passed and the piping can be covered in the North end of the building tenant rooms only
|
INSP-Sprinkler Rough-in | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PASS |
Troy Cobbley
|
|
|
The two rooms that had been covered prior to a tenting inspection are now approved for cover
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2017 | 5/18/2017 | 5/18/2017 | A | PASS |
Troy Cobbley
|
|
|
24 hr air test for the dry system passed
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2017 | 5/17/2017 | 5/17/2017 | A | PART |
Troy Cobbley
|
|
|
Air test started at 7:30am with 43psi on both dry systems
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PASS |
Troy Cobbley
|
|
|
Wet system hydro test passed. Also the sprinkler heads that have been added to the combustible concealed spaces above the fire places are ok to cover.
|
INSP-Conference | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas marked OK where tenting has passed inspection and the piping can be covered. Herb and I also discussed making the fake beams out of non-combustible material so that sprinkler protection will not be required inside.
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | PASS |
Troy Cobbley
|
|
|
The remaining rough-in for the wet system basically passed with some small items that need addressed. First the plans/calculations need to be re-approved showing the additional 90's and the combustible concealed spaces at the columns and fire places need addressed. Also four dry pendants have not been installed which also needs approved.
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | PASS |
Troy Cobbley
|
|
|
200psi test of both dry systems passed
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | FAIL |
Troy Cobbley
|
|
|
24 hour air test failed.
|
INSP-Sprinkler Rough-in | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | PART |
Jim Page
|
|
|
24 hour air test started at 0930, west dry pipe riser at 42 psi, east at 40 psi. Partail rough in inspection completed on wet and dry systems, notated city approved drawings with red ink area's that were inspected, tenting to be installed at a later date for wet system on area's inspected (Piping cannot be covered until tenting is complete and inspected). Notated city approved drawings 2 units where the tenting was complete, area's noted tenting completion are approved for cover.
|
INSP-Sprinkler Rough-in | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for two rooms marked ok where piping can be covered at the south end of the project. Also the new canopy over the main entrance can be covered
|
INSP-Sprinkler Rough-in | 4/17/2017 | 4/17/2017 | 4/17/2017 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for annotations with todays date where sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 4/10/2017 | 4/11/2017 | 4/11/2017 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the same area as previously inspected but for tenting. All tenting in this area is ok except one small spot. I discussed with Herb that prior to a cover inspection being given I need verification of insulation in the eaves to keep the sprinkler coverage with-in the 30' requirements and to verify insulation in the dog houses.
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2017 | 3/30/2017 | 3/30/2017 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans with notations in red for areas of the wet system and dry system inspected. I noted that I need access to the dog houses to verify insulation, sway bracing attachment needs to be verified. Tenting had been started but was not complete so all tenting will need to be verifed. Also the wet system remote area needs re-verified due to pipe routing changes near the closet area on the most remote line in the hydraulic calc. area.
|