INSP-Final Inspection | 8/17/2017 | 8/17/2017 | 8/17/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/2/2017 | 8/3/2017 | 8/3/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed. Also draft stops have been fixed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | PART |
Troy Cobbley
|
|
|
An overhead 24 hour air test was started at 9am with pressure marked on the guage. Piping can be covered in the low ceiling rooms except for the room where the FDC drops down due to the draft stop for the CC2 heads. This draft stop exceeds the 1,000 square foot requirement and by relocating the draft stop heads may be effected. As-builts still need to be submitted to plan review.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2017 | 7/12/2017 | 7/12/2017 | A | PART |
Troy Cobbley
|
|
|
The overhead hydro passed and rough to cover inspection failed due to the draft stops obstructing the CC2 heads. Also the floor plan does not match and the inspectors test is not shown so as-builts are needed for the next inspection and also for the plan reviewer.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for underground supply complete.
|
INSP-Supply line flush | 6/20/2017 | 6/21/2017 | 6/21/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in | 6/19/2017 | 6/20/2017 | 6/20/2017 | P | PART |
Jim Page
|
|
|
Previously noted item with sprigs has been corrected, high ceiling in gym area approved for cover.
|
INSP-Sprinkler Rough-in | 6/16/2017 | 6/19/2017 | 6/19/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete, sprigs along east wall of gym are over 48 inches requiring bracing, reast of gym area approved for cover as noted on the city approved drawings.
|
INSP-Sprinkler Rough-in | 5/24/2017 | 5/25/2017 | 5/25/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover
|