INSP-Final Inspection | 12/12/2018 | 12/13/2018 | 12/12/2018 | A | PASS |
Jim Page
|
|
|
Final undergorund supply inspection complete.
Overhead was finaled and we realized this was complete also. Please call Adam with questions Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Supply line flush | 6/18/2018 | 6/20/2018 | 6/20/2018 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete.
Lonnie. Please schedule for 10 AM Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover. Insulator will need to provide documentation for compatibility of spray foam insulation and CPVC.
|
INSP-Sprinkler Rough-in | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | CANC |
Jim Page
|
|
|
Inspection request was suppose to be scheduled for 13MAR2018 for the AM per conversation with general contractor Greg phone# ###-####. This request is cancelled and rescheduled for the correct coordinated date and time.
|
INSP-Sprinkler Rough-in | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|