Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberFIR18-00448
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 2817 S FEATHERLY WAY
Project NameNXEDGE BOISE LAB TI
Customer Number 
ePlanReviewYes
Description
[Nxedge Boise Lab TI]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration. Install an addition to the existing system to cover the new clean room.

[BLD18-00955]
Permit to remodel to create a 3,889 sq. ft. cleanroom manufacturing area within the existing 32,350 sq. ft. building. Approval is contingent upon adhering to the approved plans on file and attached engineering. Work to include: construction of interior nonbearing area demising walls, select new door/door frames, installation of pre-manufactured cleanroom walls and roof panels to create a corridor, packing room, a metrology room, a QC room, a presentation area, a cleaning room, an unpacking room and a gowning room, select new interior design footings, framing and columns, select interior viewing windows, structural modifications to roof structure for new roof mechanical equipment, new light fixtures, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the current IBC. Note: Special inspection required see attached form 310. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/15/20188/17/20188/17/2018APASS
DetailsJim Page
Previously noted items have been completed, final fire sprinkler inspection complete.

Please call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Final Inspection8/9/20188/10/20188/10/2018PFAIL
DetailsJim Page
Three heads in clean room are overspace @ 144 square feet, heads need to be relocated to 130 square feet or less. Pass-through section between clean room and hallway requires fire sprinklers to be installed per conversation with Tim Frost Fire sprinkler plan reviewer.



Call Anthony to coordinate Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro8/9/20188/10/20188/10/2018PDONE
DetailsJim Page
Hydrostatic test for newly installed overhead fire sprinkler piping witnessed, no pressure loss observed at contractor provided gauge.

Call Anthony to coordinate Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro6/25/20186/26/20186/26/2018APART
DetailsTroy Cobbley
The rough-in for the mains and branchlines passed. Missing one earthquake brace at the drop down to the clean room. Need as-builts due to two addtional 90's in the 4" feed main just outside of the riser room. Will need another rough to cover inspection when the flex heads are installed. Not able to do the hydro test due to fhe flex heads not being installed.


Call Anthony to coordinate, thanks Phone #: ###-#### Inspection requested via web by Anthony Minichiello