INSP-Final Inspection | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 6/12/2019 | 6/14/2019 | 6/14/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide the auto resetting tamper switches as discussed and the overhead and underground test papers.
please call James. Thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 6/10/2019 | 6/11/2019 | 6/11/2019 | P | PART |
Jim Page
|
|
|
Partial final inspection for fire sprinklers complete, all escutcheons are placed with no gaps, permit addressing has been corrected. Could not complete inspection due to fire alarm contractor not requesting an inspection. Remaining items to inspect will be all fire alarm associated itmes with the fire sprinkler system. Per conversation with Ron Johnson, FDC bell will remain in current location.
Final inspection pending passing underground rough/hydro in AM. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 6/10/2019 | 6/11/2019 | 6/11/2019 | A | DONE |
Jim Page
|
|
|
Undergorund hydrostatic test witnessed, no pressure loss observed. Underground repair approved for cover.
Underground rough/hydro after repair. Call James to coordinate Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Supply line flush | 6/10/2019 | 6/11/2019 | 6/11/2019 | A | DONE |
Jim Page
|
|
|
Main supply flush completed on 10JUNE2019.
8am with Stacy at Suez. Call James if anything comes up Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Supply line flush | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
INSP-Supply line flush | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | FAIL |
Jim Page
|
|
|
Follow up coordination did not happen with SUEZ, no flush was performed, this request will need to be rescheduled and ccoordinated accordingly.
RE-flush at 2pm with Suez due to underground repair. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Supply line flush | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Troy Cobbley
|
|
|
I witnessed the underground supply line flush
|
INSP-Sprinkler Rough-in | 3/5/2019 | 3/6/2019 | 3/6/2019 | A | PASS |
Troy Cobbley
|
|
|
Tenting has been repaired. Piping can be covered. Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/1/2019 | 3/4/2019 | 3/4/2019 | P | FAIL |
Troy Cobbley
|
|
|
Tenting failed again, not all piping has been covered. No piping to be covered until a tenting inspection has passed.
Call Anthony before you head out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 2/26/2019 | 2/27/2019 | 2/27/2019 | P | FAIL |
Troy Cobbley
|
|
|
Rough in passed with one exception on 2nd floor apt that Anthony will reseearch on possible obstruction. Tenting will need to be fixed in several areas lacking coverage. No piping to be covered,.
Call Anthony before heading out. Recheck based on Plan-Mod approval. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough/hydro for the detached units passed. Piping can not be covered until a tenting inspection has been passed and plan mods are approved for the added pendant head in the second floor remote area. Call Anthony before heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 2/14/2019 | 2/15/2019 | 2/15/2019 | P | PART |
Jim Page
|
|
|
Hydrostatic test for levels 1 and 2 overehad fire sprinkler piping witnessed, no pressure loss observed, no other inspections were perfromed.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2018 | 9/17/2018 | 9/18/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground rough/hydro. Call Anthony with a time, will be ready this morning Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
_____________
Udg installation appeard to be adequate.
One hydro held fine, no loss.
The second hydro was low when I arrived. The contractor showed up and fixed a leak where the guage was connected. When I arrived the second time the UDG appeared to be holding pressure. I saw no visible leakeage.
|