INSP-Final Inspection | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 6/3/2019 | 6/4/2019 | 6/4/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 5/30/2019 | 5/31/2019 | 5/31/2019 | A | CANC |
Troy Cobbley
|
|
|
Could not get access to the building. Will need to be rescheduled. Phone #: ###-#### Inspection requested via web by Sam Ball
|