Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberFIR19-00623
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 924 W MCGREGOR CT
Project NameAceCo Manufacturing
Customer Number 
ePlanReviewYes
Description
New metal manufacturing building with 3 systems 2 wet and 1 dry
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/15/20207/16/20207/16/2020APASS
DetailsJim Page
Final fire sprinkler inspection is complete.

Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Final Inspection7/14/20207/15/20207/15/2020PCANC
DetailsJim Page
Could not perform inspection due too manpower shortage, inspection is rescheduled for 16JULY2020, this request is cancelled.

Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Sprinkler Rough-in/Hydro7/8/20207/8/20207/8/2020PPASS
DetailsTroy Cobbley
System #1 overhead hydro witnessed with no pressure loss.

Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Sprinkler Rough-in7/1/20207/2/20207/2/2020APASS
DetailsJim Page
Remaining rough to cover inspection is complete, approved for cover.

system #1 Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Sprinkler Rough-in/Hydro6/16/20206/17/20206/17/2020APART
DetailsJim Page
24 hour air test is complete with no visible loss of pressure at riser provided gauge.

24 hour air test - screened // Rick Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro6/15/20206/16/20206/16/2020APART
DetailsJim Page
Hydrostatic test witnessed for dry system and wet system number 2, no pressure loss observed at riser provided gauges. 24 hour air test started for dry stsrtem at 2PM with 45PSI on gauge.

Rick *screened* Phone #: ###-####
INSP-Sprinkler Rough-in5/20/20205/21/20205/21/2020APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler below southwest mezzanine complete, area inspected approved for cover.

Rick Phone #: ###-####
INSP-Sprinkler Rough-in5/18/20205/20/20205/20/2020ACANC
DetailsTroy Cobbley
Cancel per Rick. This is rough in for west mezzanine piping.
Please call Rick Fry with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Sprinkler Rough-in5/18/20205/19/20205/19/2020PCANC
DetailsJim Page
Cancelled per conversation with point of contact, inspection was scheduled for 20MAY2020.

This is rough in for main building overhead.
Please call Rick Fry with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Sprinkler Rough-in5/18/20205/18/20205/18/2020PPART
DetailsJim Page
Rough in inspection for system 1 is complete. Overhead fire sprinkler piping in restroom hardlids inspected, restroom hardlids approved for cover.

This is rough in for ceiling areas at offices.
Please call Rick Fry with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Supply line flush9/24/20199/24/20199/24/2019PDONE
DetailsJim Page
Underground main line flush complete.

will work with Stacy on time Phone #: ###-#### Inspection requested via web by Matthew Lewis